13301 W VENTURA BLVD 91423
Certificate Information: 13301 W VENTURA BLVD 91423
- Application / Permit
- 25010-10000-00780
- Plan Check / Job No.
- B25LA06484
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Outdoor Dining Area (Al Fresco)
- Work Description
- NEW OUTDOOR COVERED AL FRESCO DINING AREA. NEW RESTROOM/BAR AREA.
- Permit Issued
- Issued on 10/8/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2025 | KEVIN MORALES |
| Assigned to Zoning Architect | 2/20/2025 | KEVIN MORALES |
| Corrections Issued | 2/26/2025 | KEVIN MORALES |
| Quality Review Completed | 2/26/2025 | EUGENE BARBEAU |
| Building Plans Picked Up | 3/3/2025 | APPLICANT |
| Plan Check Approved | 10/8/2025 | KEVIN MORALES |
| Issued | 10/8/2025 | APPLICANT |
| CofO in Progress | 3/4/2026 | RICKEY JACKSON |
| Permit Finaled | 3/4/2026 | RICKEY JACKSON |
| CofO Issued | 3/4/2026 | RICKEY JACKSON |
| Permit Finaled | 3/4/2026 | RICKEY JACKSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/5/2025 | BIAINA HARITUNIAN |
| Watercourse | Cleared | 3/5/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/8/2025 | BIAINA HARITUNIAN |
| DAS Clearance | Cleared | 4/10/2025 | SHINE LIN |
| ZA Case | Cleared | 8/14/2025 | ASHLEY RODARTE |
| ZA Case | Cleared | 8/14/2025 | ASHLEY RODARTE |
| ZA Case | Cleared | 9/9/2025 | ASHLEY RODARTE |
| Food establishment approval | Cleared | 9/11/2025 | LACDHS APPROVED |
Contact Information
| Contractor | S K A V Design Inc; Lic. No.: 288619-B | 31858 CASTAIC ROAD STE 305 CASTAIC, CA 91384 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/23/2025 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 10/23/2025 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Steel/Welding | 10/27/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 11/4/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 11/7/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 11/21/2025 | Not Ready for Inspection | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 11/25/2025 | Partial Inspection | JOHN KITCKO |
| Pre-Inspection | 12/1/2025 | Approved | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Approved | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 12/22/2025 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 12/22/2025 | Not Ready for Inspection | JOHN KITCKO |
| Drywall Nailing | 12/29/2025 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 12/29/2025 | Partial Approval | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 1/14/2026 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 1/14/2026 | Partial Approval | JOHN KITCKO |
| Insulation | 1/26/2026 | Approved | JOHN KITCKO |
| Interior/Exterior Lathing | 1/26/2026 | Approved | JOHN KITCKO |
| Wood Frame | 1/26/2026 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 1/30/2026 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 1/30/2026 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 2/6/2026 | Partial Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 2/6/2026 | Partial Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 2/25/2026 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Not Ready | DEANDRE HOFFMAN |
| Smoke Detectors | 2/25/2026 | Approved | DEANDRE HOFFMAN |
| Verify Sprinkler Sign Off | 2/25/2026 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 2/25/2026 | Approved | DEANDRE HOFFMAN |
| Final | 2/27/2026 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Not Ready | JEFFREY FULTON |
| Final | 3/4/2026 | OK to Issue CofO | RICKEY JACKSON |
| SGSOV-Seismic Gas S/O Valve | 3/4/2026 | SGSOV Approved | RICKEY JACKSON |