706 S HARBOR BLVD 90731
Certificate Information: 706 S HARBOR BLVD 90731
- Application / Permit
- 25010-10000-00778
- Plan Check / Job No.
- B25LA06476
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- *eplan*Installation of HCD permitted restroom trailer at the West Harbor project. This restroom in one of two that will be installed, the other restroom permit is #25010-10000-00578
- Permit Issued
- Issued on 5/23/2025
- Issuing Office
- Current Status
- CofO Issued on 9/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | SALVADOR QUINTANILLA |
| Corrections Issued | 3/8/2025 | SALVADOR QUINTANILLA |
| Quality Review Completed | 3/14/2025 | QUAN NGHIEM |
| Plan Check Approved | 5/14/2025 | SALVADOR QUINTANILLA |
| Issued | 5/23/2025 | APPLICANT |
| Permit Finaled | 9/23/2025 | DAVID TSAU |
| CofO Issued | 9/23/2025 | DAVID TSAU |
| Permit Finaled | 9/23/2025 | DAVID TSAU |
Permit Application Clearance Information
| Highway dedication | Cleared | 3/19/2025 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 3/19/2025 | ERIK BEASLEY |
| ZA Case | Cleared | 3/21/2025 | GRACIELA ACOSTA |
| ZA Case | Cleared | 3/21/2025 | GRACIELA ACOSTA |
| "Q" conditions | Cleared | 4/1/2025 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2025 | ERIK BEASLEY |
| Port of LA Approval | Cleared | 4/7/2025 | MELISSA HARNE |
| Green Code | Cleared | 4/23/2025 | SALVADOR QUINTANILLA |
| DAS Clearance | Cleared | 4/28/2025 | ELIZABETH TOMS |
Contact Information
| Contractor | Elan Construction Inc; Lic. No.: 716606-B | 1503 CENTRE STREET SAN PEDRO, CA 90731 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 6/25/2025 | Partial Approval | DAVID TSAU |
| Footing/Foundation/Slab | 6/25/2025 | Approved | DAVID TSAU |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Not Required | DAVID TSAU |
| Smoke Detectors | 6/25/2025 | Approved | DAVID TSAU |
| Verify Sprinkler Sign Off | 6/25/2025 | Approved | DAVID TSAU |
| Wood Frame | 6/25/2025 | Approved | DAVID TSAU |