16658 W ADDISON ST 91436

Certificate Information: 16658 W ADDISON ST 91436

Application / Permit
25010-10000-00765
Plan Check / Job No.
B25LA06399
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan New 2 story SFD with attached garage
Permit Issued
Issued on 8/11/2025
Issuing Office
Current Status
Issued on 8/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/3/2025 APPLICANT
Assigned to Plan Check Engineer 3/6/2025 ARSALAN SHABESTARI
Assigned to Zoning Architect 3/6/2025 MEGAN KOLP
Corrections Issued 3/11/2025 ARSALAN SHABESTARI
Quality Review Completed 3/18/2025 PRANITA SHAH
Plan Check Approved 7/16/2025 ARSALAN SHABESTARI
Plan Check Approved 8/7/2025 INTERNET PERMIT
Issued 8/11/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/26/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 3/28/2025 SAFA JAVANMARDI
Sewer availability Cleared 3/28/2025 SAFA JAVANMARDI
Hydrant and Access approval Cleared 4/2/2025 GILBERT URREA
Low Impact Development (LID) Cleared 4/2/2025 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 4/3/2025 SAFA JAVANMARDI
Trees in Parkway Cleared 4/29/2025 MIGUEL ORNELAS
Permit Cleared 4/30/2025 SAFA JAVANMARDI
Frnt yard landscape/Water mgmt Cleared 5/20/2025 JACQUELINE TORRES
Zoning Plan Check Cleared 6/10/2025 MEGAN KOLP

Contact Information

Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/29/2025 Corrections Issued THOMAS FINNILA
Underground Mechanical 9/29/2025 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 10/1/2025 Conditional Approval THOMAS FINNILA
Deputy Other (see comments) 10/6/2025 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 10/8/2025 Approved THOMAS FINNILA
Sewer 10/8/2025 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/1/2025 Not Ready for Inspection THOMAS FINNILA
Deputy Wood Construction 12/5/2025 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Partial Approval THOMAS FINNILA
PLUMBING-Rough 12/10/2025 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/15/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 12/15/2025 Approved THOMAS FINNILA
ELECTRICAL-Rough 12/31/2025 Approved GEVORK IPCHYAN
HVAC-Rough 12/31/2025 Approved GEVORK IPCHYAN
Shower Pan 12/31/2025 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 1/20/2026 Not Ready for Inspection THOMAS FINNILA
Insulation 1/28/2026 Approved THOMAS FINNILA
Interior/Exterior Lathing 1/28/2026 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 2/6/2026 Approved THOMAS FINNILA