16252-16254 W ADDISON ST 91436
Certificate Information: 16252-16254 W ADDISON ST 91436
- Application / Permit
- 25010-10000-00650
- Plan Check / Job No.
- B25LA05566
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN***PROPOSED SINGELE FAMILY DWELLING WITH ATTACHED GARAGE AND ACCESSORY DWELLING UNIT PER GC 66323(a)(1)
- Permit Issued
- Issued on 5/15/2025
- Issuing Office
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | SINA KHOSRAVI |
| Corrections Issued | 2/18/2025 | SINA KHOSRAVI |
| Quality Review Completed | 2/19/2025 | GARO TELMI |
| Plan Check Approved | 5/8/2025 | SINA KHOSRAVI |
| Issued | 5/15/2025 | APPLICANT |
| CofO in Progress | 3/18/2026 | THOMAS FINNILA |
| Permit Finaled | 5/22/2026 | JOHN JANSON |
| CofO Issued | 5/22/2026 | JOHN JANSON |
| Permit Finaled | 5/22/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/25/2025 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 2/28/2025 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/28/2025 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 3/5/2025 | JERRY KAO |
| Construction near power lines | Cleared | 4/1/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/30/2025 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/9/2025 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/12/2025 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Partial Approval | JON MCHUGH |
| Deputy Steel/Welding | 7/2/2025 | Conditional Approval | JON MCHUGH |
| ELECTRICAL-Rough | 8/20/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 8/20/2025 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/2/2025 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 9/2/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Wood Construction | 9/4/2025 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 9/5/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Corrections Issued | ROBERT GOLD |
| HVAC-Rough | 9/9/2025 | Corrections Issued | ROBERT GOLD |
| Shower Pan | 9/11/2025 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 9/16/2025 | Corrections Issued | THOMAS FINNILA |
| Shower Pan | 9/16/2025 | Approved | THOMAS FINNILA |
| Wood Frame | 9/16/2025 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 9/24/2025 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/24/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 9/24/2025 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/30/2025 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/3/2025 | Approved | THOMAS FINNILA |
| Green Building Rough | 10/3/2025 | Approved | THOMAS FINNILA |
| Insulation | 10/3/2025 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 10/3/2025 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/9/2025 | Approved | MORRIS JACKSON |
| Drywall Nailing | 10/15/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 2/19/2026 | Not Ready for Inspection | JON MCHUGH |
| Final | 2/19/2026 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 2/19/2026 | Approved | JON MCHUGH |
| Green Building Final | 2/19/2026 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 2/19/2026 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 2/19/2026 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 2/19/2026 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 2/19/2026 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 3/4/2026 | Approved | THOMAS FINNILA |
| Gas Test | 3/4/2026 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 3/4/2026 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 3/4/2026 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 3/6/2026 | Approved | THOMAS FINNILA |
| Final | 3/6/2026 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 3/6/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Service/Power Release | 3/6/2026 | Approved | THOMAS FINNILA |
| Final | 3/17/2026 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 3/17/2026 | Approved | THOMAS FINNILA |
| HVAC-Final | 3/17/2026 | Approved | THOMAS FINNILA |
| Special/Order Compliance | 5/11/2026 | Corrections Issued | SEAN WIRCH |