543 S MORENO AVE 90049

Certificate Information: 543 S MORENO AVE 90049

Application / Permit
25010-10000-00648
Plan Check / Job No.
B25LA05562
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
New detached 1 story recreation room.
Permit Issued
Issued on 9/19/2025
Issuing Office
Metro
Current Status
Issued on 9/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/12/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 ARMEN JIVALAGIAN
Corrections Issued 2/18/2025 ARMEN JIVALAGIAN
Quality Review Completed 2/21/2025 PETER KIM
Building Plans Picked Up 3/5/2025 APPLICANT
Applicant returned to address corrections 3/17/2025 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/7/2025 ARMEN JIVALAGIAN
Plan Check Approved 9/18/2025 ARMEN JIVALAGIAN
Issued 9/19/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/2/2025 DIANA RENTERIA
Sewer availability Cleared 6/2/2025 DIANA RENTERIA
Roof/Waste drainage to street Cleared 6/24/2025 SAFA JAVANMARDI
Specific Plan Cleared 7/14/2025 PEDRO AYALA
Miscellaneous Cleared 7/21/2025 ALEX VELA

Contact Information

Architect Oreck,, Kevin Robert; Lic. No.: C23895 1008 LARKER AVE      LOS ANGELES, CA 90042
Contractor Lannen Construction Inc; Lic. No.: 811038-B 1545 SAWTELLE BLVD STE 22      LOS ANGELES, CA 90025
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024
Engineer Tsai,, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Shotcrete 12/11/2025 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 1/27/2026 Approved MICHAEL ALLEN
Footing/Foundation/Slab 1/27/2026 Approved MICHAEL ALLEN
Underground Mechanical 1/27/2026 Approved MICHAEL ALLEN
PLUMBING-Rough 1/28/2026 Approved MICHAEL ALLEN
Footing/Foundation/Slab 2/6/2026 Approved MICHAEL ALLEN
Underground Mechanical 2/23/2026 Approved MICHAEL ALLEN
Deputy Drilled-In Anchors 3/13/2026 Conditional Approval ANDREW NAVE
Deputy Wood Construction 3/13/2026 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 3/16/2026 Partial Approval DANIEL VERA
Special/Order Compliance 4/7/2026 Partial Inspection RYAN SALAZAR
HVAC-Rough 4/10/2026 Corrections Issued EVAN COOPER
PLUMBING-Rough 4/10/2026 Approved EVAN COOPER
BUILDING-Rough-Frame 4/13/2026 Conditional Approval MICHAEL ALLEN
ELECTRICAL-Rough 4/13/2026 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/13/2026 Approved MICHAEL ALLEN
Green Building Rough 4/13/2026 Not Ready for Inspection MICHAEL ALLEN
HVAC-Rough 4/13/2026 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 4/23/2026 Approved MICHAEL ALLEN
Green Building Rough 4/23/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 4/23/2026 Partial Approval MICHAEL ALLEN
Insulation 5/4/2026 Approved ANDREW NAVE
Drywall Nailing 5/12/2026 Approved ANTHONY EGSON