5349-5351 N NOBLE AVE 91411

Certificate Information: 5349-5351 N NOBLE AVE 91411

Application / Permit
25010-10000-00616
Plan Check / Job No.
B25LA05199
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New single-story SFD per SB9 with attached ADU per LAMC 12.22 A.33 (c) and (e) the building will be fire sprinkler with NFPA-13D
Permit Issued
Issued on 8/27/2025
Issuing Office
Current Status
Issued on 8/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/13/2025 APPLICANT
Assigned to Plan Check Engineer 3/6/2025 GEORGE JOLAKIAN
Corrections Issued 3/10/2025 GEORGE JOLAKIAN
Quality Review Completed 3/17/2025 HERNAN ARREOLA
Applicant returned to address corrections 6/17/2025 GEORGE JOLAKIAN
Applicant returned to address corrections 8/6/2025 GEORGE JOLAKIAN
Applicant returned to address corrections 8/19/2025 GEORGE JOLAKIAN
Plan Check Approved 8/27/2025 GEORGE JOLAKIAN
Issued 8/27/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/20/2025 RYAN CASTRO
Senate Bill 9 Cleared 4/2/2025 JASON CHAN
ZA Case Cleared 4/2/2025 JASON CHAN
ZI Cleared 4/2/2025 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 4/4/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 4/4/2025 RYAN CASTRO
Sewer availability Cleared 4/4/2025 RYAN CASTRO
Hydrant and Access approval Cleared 4/17/2025 JERRY KAO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/22/2025 Approved JACK KARGODORIAN
Footing/Foundation/Slab 9/25/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 12/2/2025 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Partial Approval JACK KARGODORIAN
HVAC-Rough 12/2/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 12/2/2025 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 1/14/2026 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 1/14/2026 Approved JACK KARGODORIAN
Green Building Rough 1/14/2026 Approved JACK KARGODORIAN
PLUMBING-Rough 1/14/2026 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 1/14/2026 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 1/28/2026 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 1/28/2026 Approved JACK KARGODORIAN
Interior/Exterior Lathing 1/28/2026 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 1/28/2026 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 1/28/2026 Approved JACK KARGODORIAN
Insulation 2/10/2026 Approved JACK KARGODORIAN
Drywall Nailing 3/2/2026 Approved MISAEL ESPARZA
Sewer 4/21/2026 Corrections Issued MICHAEL CORTEZ
Shower Pan 4/21/2026 Not Ready for Inspection MICHAEL CORTEZ
Sewer 5/1/2026 Approved MISAEL ESPARZA
Underground Mechanical 5/1/2026 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 5/11/2026 Approved GAREN HAYRAPETYAN
Shower Pan 5/11/2026 Approved GAREN HAYRAPETYAN
Underground Mechanical 5/22/2026 Partial Approval MISAEL ESPARZA