11967-11969 W BRAY ST 90230
Certificate Information: 11967-11969 W BRAY ST 90230
- Application / Permit
- 25010-10000-00551
- Plan Check / Job No.
- B25LA04701
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Eplan. SB 9 Unit addition to (E) single family dwelling.
- Permit Issued
- Issued on 5/27/2025
- Issuing Office
- Current Status
- CofO Issued on 5/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | ALEXANDER JOO |
| Corrections Issued | 2/18/2025 | ALEXANDER JOO |
| Quality Review Completed | 2/19/2025 | GARO TELMI |
| Applicant returned to address corrections | 3/17/2025 | ALEXANDER JOO |
| Plan Check Approved | 5/27/2025 | ALEXANDER JOO |
| Issued | 5/27/2025 | APPLICANT |
| CofO in Progress | 4/23/2026 | ANTHONY EGSON |
| Permit Finaled | 5/1/2026 | RICHARD STEINBACH |
| CofO Issued | 5/1/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/1/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2025 | DARIN LAM |
| Sewer availability | Cleared | 2/22/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 3/10/2025 | DARIN LAM |
| Senate Bill 9 | Cleared | 3/11/2025 | DAVID URITA |
Contact Information
| Contractor | Neo Builders And Design Inc; Lic. No.: 1114778-B | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 5306 MULHOLLAND DRIVE SUMMERVILLE, SC 29485 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 12/1/2025 | Conditional Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 12/1/2025 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Subgrade | 12/1/2025 | Approved | ANTHONY EGSON |
| Underground Mechanical | 12/1/2025 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/5/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/10/2025 | Partial Approval | ANTHONY EGSON |
| METHANE-Barrier | 12/10/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/15/2026 | Approved | ANTHONY EGSON |
| HVAC-Rough | 1/15/2026 | Approved | ANTHONY EGSON |
| METHANE-Rough | 1/15/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/15/2026 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/20/2026 | Approved | ANTHONY EGSON |
| Green Building Rough | 1/20/2026 | Not Ready for Inspection | ANTHONY EGSON |
| MERV13>=Rough | 1/20/2026 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/28/2026 | Partial Approval | DAKOTA LOW |
| BUILDING-Rough-Frame | 1/30/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 1/30/2026 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/4/2026 | Approved | ANTHONY EGSON |
| Green Building Rough | 2/4/2026 | Approved | ANTHONY EGSON |
| Insulation | 2/5/2026 | Partial Approval | ANTHONY EGSON |
| Drywall Nailing | 2/6/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 2/6/2026 | Approved | DAKOTA LOW |
| ELECTRICAL-Final | 3/24/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 3/24/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/24/2026 | Approved | ANTHONY EGSON |
| Final | 4/7/2026 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 4/7/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 4/7/2026 | Corrections Issued | ANTHONY EGSON |
| Final | 4/15/2026 | Corrections Issued | MICHAEL ALLEN |
| Smoke Detectors | 4/15/2026 | Approved | MICHAEL ALLEN |
| Final | 4/22/2026 | OK to Issue CofO | ANTHONY EGSON |