2415 N BEACHWOOD DR 90068

Certificate Information: 2415 N BEACHWOOD DR 90068

Application / Permit
25010-10000-00535
Plan Check / Job No.
B24LA38634
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan (N) 1 story SFD per WFPP to be fully sprinklered NFPA 13D "COMPLY WITH DEPARTMENT ORDER effective date 02/26/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/10/2026
Issuing Office
Current Status
Issued on 4/10/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/10/2025 APPLICANT
Assigned to Plan Check Engineer 2/27/2025 MARCELA FRANQUEZ
Corrections Issued 3/4/2025 MARCELA FRANQUEZ
Assigned to Zoning Architect 3/6/2025 MELISSA QUINONES
Quality Review Completed 3/11/2025 HERNAN ARREOLA
Applicant returned to address corrections 9/23/2025 MARCELA FRANQUEZ
Applicant returned to address corrections 10/20/2025 MARCELA FRANQUEZ
Applicant returned to address corrections 3/27/2026 MARCELA FRANQUEZ
Plan Check Approved 4/7/2026 MARCELA FRANQUEZ
Issued 4/10/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/24/2025 PAMELA TENEZA
BHO/Hillside ordinance Cleared 3/28/2025 DAVID LOPEZ
BHO/Hillside ordinance Cleared 3/28/2025 DAVID LOPEZ
BHO/Hillside ordinance Cleared 3/28/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/28/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 3/28/2025 DAVID LOPEZ
BHO/Hillside ordinance Cleared 10/14/2025 ALBERT TAM
BHO/Hillside ordinance Cleared 10/14/2025 ALBERT TAM
Watercourse Cleared 11/4/2025 TERRY PHAN
Grading Pre-Inspection Cleared 11/5/2025 ROBERT PINA
Sewer availability Cleared 11/6/2025 DAVID LOPEZ
Zoning Plan Check Cleared 1/7/2026 MELISSA QUINONES
Hydrant and Access approval Cleared 3/19/2026 JERRY KAO
GPI Written Notices Cleared 3/27/2026 MARCELA FRANQUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2026 Approved JOEL ORDAZ
Footing/Foundation/Slab 6/11/2026 Approved JOEL ORDAZ
PLUMBING-Rough 6/11/2026 Approved JOEL ORDAZ
BUILDING-Rough-Frame 7/10/2026 Not Ready for Inspection JOEL ORDAZ
ELECTRICAL-Rough 7/10/2026 Approved JOEL ORDAZ
Green Building Rough 7/10/2026 Not Ready for Inspection JOEL ORDAZ
PLUMBING-Rough 7/10/2026 Approved JOEL ORDAZ
Verify Sprinkler Sign Off 7/10/2026 Not Ready for Inspection JOEL ORDAZ
Insulation 7/16/2026 Approved JOEL ORDAZ
Interior/Exterior Lathing 7/16/2026 Approved JOEL ORDAZ