12007 W ROSE AVE 90066
Certificate Information: 12007 W ROSE AVE 90066
- Application / Permit
- 25010-10000-00521
- Plan Check / Job No.
- B25LA04400
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [ePlan] New 2- Story SFD with attached 2-Car Garage. -Bldg Sprinklered Thru-out
- Permit Issued
- Issued on 5/8/2025
- Issuing Office
- Current Status
- CofO Issued on 5/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 2/9/2025 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 2/13/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/15/2025 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 4/23/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 5/6/2025 | MAHNAZ NOURHASHEMI |
| Issued | 5/8/2025 | APPLICANT |
| CofO in Progress | 5/8/2026 | ANDREW NAVE |
| Permit Finaled | 5/11/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/11/2026 | RICHARD STEINBACH |
| CofO Issued | 5/11/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 2/18/2025 | BRANDON WONG |
| Address approval | Cleared | 2/21/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2025 | BIAINA HARITUNIAN |
| Permit | Cleared | 2/21/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 2/21/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 2/25/2025 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 2/27/2025 | PATRICK PEREZ |
| GPI Written Notices | Cleared | 4/15/2025 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 4/15/2025 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/27/2025 | Approved | WILBER ROSALES |
| Underground Mechanical | 6/27/2025 | Approved | WILBER ROSALES |
| Footing/Foundation/Slab | 7/10/2025 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/25/2025 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2025 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Structural Steel Frame | 8/6/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 8/14/2025 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Conditional Approval | KIRK SANDERS |
| HVAC-Final | 9/2/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 9/2/2025 | Approved | KIRK SANDERS |
| Structural Steel Frame | 9/2/2025 | Corrections Issued | KIRK SANDERS |
| Gas Test | 9/4/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 9/4/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 9/10/2025 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 9/10/2025 | Approved | KIRK SANDERS |
| Green Building Rough | 9/10/2025 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 9/10/2025 | Not Ready for Inspection | KIRK SANDERS |
| Drywall Nailing | 9/11/2025 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/17/2025 | Conditional Approval | KIRK SANDERS |
| Green Building Rough | 9/17/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 9/17/2025 | Partial Approval | KIRK SANDERS |
| Shower Pan | 9/17/2025 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 9/17/2025 | Approved | KIRK SANDERS |
| Shower Pan | 9/18/2025 | Not Ready for Inspection | DANIEL VERA |
| Insulation | 9/24/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Insulation | 9/25/2025 | Approved | KIRK SANDERS |
| Drywall Nailing | 9/29/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 9/29/2025 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 4/28/2026 | Approved | EVAN COOPER |
| HVAC-Final | 4/28/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/28/2026 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 5/4/2026 | Approved | ANTHONY EGSON |
| Final | 5/4/2026 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 5/4/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/4/2026 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 5/4/2026 | Approved | ANTHONY EGSON |
| Smoke Detectors | 5/4/2026 | Approved | ANTHONY EGSON |
| Final | 5/6/2026 | OK to Issue CofO | ANTHONY EGSON |
| Final | 5/8/2026 | Conditional Approval | ANTHONY EGSON |