413 N VIA DE LA PAZ 90272

Certificate Information: 413 N VIA DE LA PAZ 90272

Application / Permit
25010-10000-00444
Plan Check / Job No.
B25LA03816
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE PER LAMC 12.23.5(B)
Permit Issued
Issued on 6/12/2025
Issuing Office
West Los Angeles
Current Status
Issued on 6/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/3/2025 APPLICANT
Assigned to Plan Check Engineer 2/4/2025 KEVIN MORALES
Corrections Issued 2/5/2025 KEVIN MORALES
Quality Review Completed 2/6/2025 EUGENE BARBEAU
Applicant returned to address corrections 5/21/2025 KEVIN MORALES
Plan Check Approved 6/6/2025 KEVIN MORALES
Issued 6/12/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/10/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/10/2025 CARLOS AGUILERA
Sewer availability Cleared 2/10/2025 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/22/2025 JERRY KAO

Contact Information

Contractor J L M Development; Lic. No.: 1025019-B 984 MONUMENT STREET   SUITE 102    PACIFIC PALISADES, CA 90272
Engineer Le,, Thang Huu; Lic. No.: NA4978       ,

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/27/2025 Approved MEL KHACHATOURIAN
Special/Order Compliance 7/24/2025 Corrections Issued KENNETH NAGLE
Special/Order Compliance 7/28/2025 Partial Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 8/15/2025 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 8/27/2025 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 8/29/2025 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 9/4/2025 Partial Approval MEL KHACHATOURIAN
Deputy Wood Construction 9/17/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 9/24/2025 Conditional Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Partial Approval STEPHANIE SWANSON
Deputy Wood Construction 10/31/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 11/4/2025 Partial Approval STEPHANIE SWANSON
Deputy Wood Construction 11/7/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 12/12/2025 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 12/23/2025 Conditional Approval STEPHANIE SWANSON
HVAC-Rough 12/23/2025 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 12/23/2025 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 1/2/2026 Approved STEPHANIE SWANSON
Green Building Rough 1/2/2026 Approved STEPHANIE SWANSON
PLUMBING-Rough 1/2/2026 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 1/2/2026 Approved STEPHANIE SWANSON
Insulation 1/14/2026 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 1/14/2026 Partial Approval STEPHANIE SWANSON
Shower Pan 1/14/2026 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 1/15/2026 Approved STEPHANIE SWANSON
Shower Pan 1/15/2026 Approved STEPHANIE SWANSON
Drywall Nailing 1/23/2026 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 5/11/2026 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 5/13/2026 Approved STEPHANIE SWANSON
Underground Mechanical 5/18/2026 Partial Approval STEPHANIE SWANSON
Sewer 5/22/2026 Approved STEPHANIE SWANSON
PLUMBING-Rough 6/18/2026 Partial Approval STEPHANIE SWANSON