635 N ERSKINE DR 90272

Certificate Information: 635 N ERSKINE DR 90272

Application / Permit
25010-10000-00413
Plan Check / Job No.
B25LA03578
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**2025 Wildfire Rebuild Eligible Project** (N) 28' X 44'-7.5" 2-STORY ACCESSORY DWELLING UNIT OVER 4-CAR GARAGE PER LAMC12.22A33(c)(d). (NFPA-13D FIRE SPRINKLERS THROUGHOUT).
Permit Issued
Issued on 6/25/2025
Issuing Office
Current Status
CofO Issued on 6/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2025 APPLICANT
Assigned to Plan Check Engineer 2/4/2025 RAPHAEL ROSAS
Corrections Issued 2/5/2025 RAPHAEL ROSAS
Quality Review Completed 2/5/2025 STEVEN KIM
Applicant returned to address corrections 4/28/2025 RAPHAEL ROSAS
Plan Check Approved 6/10/2025 RAPHAEL ROSAS
No Progress 6/10/2025 RAPHAEL ROSAS
Plan Check Approved 6/10/2025 RAPHAEL ROSAS
Issued 6/25/2025 APPLICANT
CofO in Progress 6/22/2026 MEL KHACHATOURIAN
Permit Finaled 6/29/2026 JUAN VALENZUELA
CofO Issued 6/29/2026 JUAN VALENZUELA
Permit Finaled 6/29/2026 JUAN VALENZUELA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/23/2025 OSCAR GUTIERREZ
Roof/Waste drainage to street Cleared 4/23/2025 OSCAR GUTIERREZ
Sewer availability Cleared 4/23/2025 OSCAR GUTIERREZ
Hydrant and Access approval Cleared 5/1/2025 LAVEON RIDER

Contact Information

Architect Palka,, Joseph Anthony; Lic. No.: NA24276       ,
Contractor Owner-Builder       ,
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Engineer Phillips,, Craig; Lic. No.: NA69673       ,

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/17/2025 Approved MEL KHACHATOURIAN
Footing/Foundation/Slab 8/4/2025 Partial Approval BOBBY KEY
Deputy Reinf. Concrete 8/5/2025 No Access for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 8/15/2025 Approved STEPHANIE SWANSON
Deputy Reinf. Concrete 8/18/2025 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 12/1/2025 Partial Approval MEL KHACHATOURIAN
Green Building Rough 12/1/2025 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 12/1/2025 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 12/22/2025 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval MEL KHACHATOURIAN
Green Building Rough 12/22/2025 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 12/22/2025 Approved MEL KHACHATOURIAN
PLUMBING-Rough 12/22/2025 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 12/22/2025 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 1/28/2026 Approved MEL KHACHATOURIAN
Green Building Rough 1/28/2026 Approved MEL KHACHATOURIAN
Insulation 2/6/2026 Corrections Issued DANIEL VERA
Drywall Nailing 2/11/2026 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 2/11/2026 Partial Approval MEL KHACHATOURIAN
Shower Pan 3/24/2026 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 4/1/2026 Approved EVAN COOPER
Gas Test 4/8/2026 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 5/28/2026 Conditional Approval MEL KHACHATOURIAN
Final 5/28/2026 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Final 5/28/2026 Approved MEL KHACHATOURIAN
HVAC-Final 5/28/2026 Conditional Approval MEL KHACHATOURIAN
PLUMBING-Final 5/28/2026 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 5/28/2026 SGSOV Approved MEL KHACHATOURIAN
Service/Power Release 5/28/2026 Conditional Approval MEL KHACHATOURIAN
Smoke Detectors 5/28/2026 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 6/11/2026 Approved MEL KHACHATOURIAN
Service/Power Release 6/11/2026 Approved MEL KHACHATOURIAN
Final 6/22/2026 OK to Issue CofO MEL KHACHATOURIAN