630 N LAS CASAS AVE 90272

Certificate Information: 630 N LAS CASAS AVE 90272

Application / Permit
25010-10000-00372
Plan Check / Job No.
B25LA03169
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY NFPA-13D
Permit Issued
Issued on 6/12/2025
Issuing Office
Valley
Current Status
Issued on 6/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/30/2025 APPLICANT
Assigned to Plan Check Engineer 2/4/2025 RARES BODEA
Corrections Issued 2/4/2025 RARES BODEA
Quality Review Completed 2/6/2025 STEVEN KIM
Applicant returned to address corrections 4/21/2025 RARES BODEA
Applicant returned to address corrections 5/13/2025 RARES BODEA
Plan Check Approved 5/21/2025 RARES BODEA
Issued 6/12/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/10/2025 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 2/10/2025 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 2/10/2025 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 2/10/2025 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 2/10/2025 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 2/10/2025 HISASHI KOBAYAKAWA
Sewer availability Cleared 2/10/2025 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 3/3/2025 LAVEON RIDER
Eng Process Fee Ord 176,300 Cleared 3/17/2025 HISASHI KOBAYAKAWA

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/21/2025 Partial Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 7/29/2025 Corrections Issued STEPHANIE SWANSON
Reinforced Concrete Frame 9/16/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 10/15/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 10/17/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 10/31/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 11/13/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2025 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Partial Approval MEL KHACHATOURIAN
Deputy Wood Construction 2/3/2026 Conditional Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Partial Approval MEL KHACHATOURIAN
Wood Frame 2/4/2026 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 2/18/2026 Approved MEL KHACHATOURIAN
PLUMBING-Rough 3/10/2026 Approved EVAN COOPER
ELECTRICAL-Rough 3/12/2026 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 3/12/2026 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 3/16/2026 Approved MEL KHACHATOURIAN
HVAC-Rough 3/16/2026 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 3/17/2026 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 3/17/2026 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 3/17/2026 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 4/3/2026 Approved MICHAEL ALLEN
Green Building Rough 4/3/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 4/3/2026 Partial Approval MICHAEL ALLEN
Verify Sprinkler Sign Off 4/3/2026 Approved MICHAEL ALLEN
Insulation 4/27/2026 Conditional Approval DANIEL VERA
Drywall Nailing 5/5/2026 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 5/5/2026 Approved MEL KHACHATOURIAN
Shower Pan 5/5/2026 Approved MEL KHACHATOURIAN