409-409 1/2 E 104TH ST 90003
Certificate Information: 409-409 1/2 E 104TH ST 90003
- Application / Permit
- 25010-10000-00312
- Plan Check / Job No.
- B25LA02626
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- *ePlan* New 2-story duplex with attached 2 car and 1 car garages. To be sprinklered thru-out with NFPA-13D
- Permit Issued
- Issued on 6/17/2025
- Issuing Office
- Current Status
- CofO Issued on 12/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | MATTHEW TORRES |
| Corrections Issued | 2/1/2025 | MATTHEW TORRES |
| Quality Review Completed | 2/4/2025 | GARO TELMI |
| Applicant returned to address corrections | 4/23/2025 | MATTHEW TORRES |
| Plan Check Approved | 6/2/2025 | MATTHEW TORRES |
| Issued | 6/17/2025 | APPLICANT |
| CofO in Progress | 12/3/2025 | ARTHUR NEGRETE |
| Permit Finaled | 12/8/2025 | ANSON MAGLASANG |
| CofO Issued | 12/8/2025 | ANSON MAGLASANG |
| Permit Finaled | 12/8/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/15/2025 | JERRY KAO |
| Low Impact Development (LID) | Cleared | 2/20/2025 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2025 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 2/22/2025 | JOSE HERNANDEZ |
| SB8 RUD | Cleared | 2/26/2025 | KENNETH LE |
| Address approval | Cleared | 3/26/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 3/27/2025 | ABEL CASILLAS |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/3/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Reinf. Concrete | 7/7/2025 | Conditional Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/7/2025 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/7/2025 | Approved | ANTHONY EGSON |
| Sewer | 7/10/2025 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 7/10/2025 | Approved | EUGENE CASSIDY |
| Wood Frame | 7/10/2025 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Partial Approval | ANTHONY EGSON |
| Insulation | 7/11/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2025 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/28/2025 | Approved | ANTHONY EGSON |
| HVAC-Rough | 8/28/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/29/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 8/29/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 8/29/2025 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 8/29/2025 | Approved | ANTHONY EGSON |
| Insulation | 9/2/2025 | No Access for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/3/2025 | No Access for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/5/2025 | Corrections Issued | ANTHONY EGSON |
| Insulation | 9/5/2025 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/8/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/9/2025 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/10/2025 | Approved | ANTHONY EGSON |
| Insulation | 9/15/2025 | Corrections Issued | ANTHONY EGSON |
| Insulation | 9/17/2025 | Partial Inspection | ANTHONY EGSON |
| Insulation | 9/18/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 9/25/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/25/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/2/2025 | Approved | ARTHUR NEGRETE |
| Final | 12/2/2025 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 12/2/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 12/2/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 12/2/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Not Required | ARTHUR NEGRETE |
| Service/Power Release | 12/2/2025 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 12/2/2025 | Approved | ARTHUR NEGRETE |