7019-7021 S ESTRELLA AVE 90044
Certificate Information: 7019-7021 S ESTRELLA AVE 90044
- Application / Permit
- 25010-10000-00308
- Plan Check / Job No.
- B25LA02617
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- *ePlan* New 2-story duplex with attached 3 car garage. To be sprinklered thru-out with NFPA-13D.
- Permit Issued
- Issued on 10/22/2025
- Issuing Office
- Current Status
- CofO Issued on 5/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | MATTHEW TORRES |
| Corrections Issued | 2/1/2025 | MATTHEW TORRES |
| Quality Review Completed | 2/6/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 10/14/2025 | MATTHEW TORRES |
| Applicant returned to address corrections | 10/15/2025 | MATTHEW TORRES |
| Plan Check Approved | 10/20/2025 | MATTHEW TORRES |
| Issued | 10/22/2025 | APPLICANT |
| CofO in Progress | 5/13/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 5/16/2026 | DEROLD HAUFF |
| CofO Issued | 5/16/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/15/2025 | LAVEON RIDER |
| Address approval | Cleared | 2/21/2025 | TAL SHEMEN |
| Low Impact Development (LID) | Cleared | 2/21/2025 | ERNEST TSE |
| Permit | Cleared | 2/21/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 2/25/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 2/25/2025 | TAL SHEMEN |
| SB8 RUD | Cleared | 10/3/2025 | ASHLEY MEDINA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/4/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 11/4/2025 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 11/5/2025 | Corrections Issued | BARRY HACHE |
| Deputy Reinf. Concrete | 11/6/2025 | Conditional Approval | BARRY HACHE |
| Underground Mechanical | 11/12/2025 | Not Ready for Inspection | BARRY HACHE |
| Wood Frame | 11/12/2025 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 11/14/2025 | No Access for Inspection | BARRY HACHE |
| PLUMBING-Rough | 11/17/2025 | Corrections Issued | BARRY HACHE |
| Sewer | 11/17/2025 | Approved | BARRY HACHE |
| Underground Mechanical | 11/17/2025 | Not Ready for Inspection | BARRY HACHE |
| Wood Frame | 11/17/2025 | Not Ready for Inspection | BARRY HACHE |
| Underground Mechanical | 11/19/2025 | Corrections Issued | BARRY HACHE |
| Wood Frame | 11/19/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 11/24/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/8/2025 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2025 | Partial Approval | BARRY HACHE |
| Deputy Wood Construction | 12/30/2025 | Conditional Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 1/15/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 1/15/2026 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 1/16/2026 | Approved | BARRY HACHE |
| HVAC-Rough | 1/16/2026 | Approved | BARRY HACHE |
| PLUMBING-Rough | 1/16/2026 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 1/16/2026 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 1/20/2026 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 1/20/2026 | Partial Approval | BARRY HACHE |
| BUILDING-Rough-Frame | 1/22/2026 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2026 | Approved | BARRY HACHE |
| Insulation | 1/28/2026 | Approved | BARRY HACHE |
| Drywall Nailing | 2/3/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 2/3/2026 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 5/7/2026 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 5/7/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/7/2026 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 5/7/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 5/8/2026 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 5/8/2026 | Approved | LUIS CASTRO |
| Green Building Final | 5/8/2026 | Approved | LUIS CASTRO |
| HVAC-Final | 5/8/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 5/8/2026 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 5/13/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 5/13/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |