1830-1832 W 48TH ST 90062

Certificate Information: 1830-1832 W 48TH ST 90062

Application / Permit
25010-10000-00307
Plan Check / Job No.
B25LA02608
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
[ePlan] NEW 2-STORY DUPLEX W/ ATTACHED 3-CAR GARAGE -BLDG SPRINKLERED THRU-OUT.
Permit Issued
Issued on 7/29/2025
Issuing Office
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 MAHNAZ NOURHASHEMI
Corrections Issued 2/4/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 2/12/2025 SINA KHOSRAVI
Applicant returned to address corrections 7/11/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 7/22/2025 MAHNAZ NOURHASHEMI
Issued 7/29/2025 APPLICANT
CofO in Progress 4/27/2026 SABAS ALONSO
Permit Finaled 4/30/2026 DEROLD HAUFF
CofO Issued 4/30/2026 DEROLD HAUFF
Permit Finaled 4/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 2/24/2025 MIGUEL ORNELAS
Address approval Cleared 3/3/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 3/3/2025 CELINA MORENO
Hydrant and Access approval Cleared 3/5/2025 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 3/10/2025 CELINA MORENO
Permit Cleared 3/12/2025 CELINA MORENO
Sewer availability Cleared 3/19/2025 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/22/2025 Approved BRENDAN MORELLI
Footing/Foundation/Slab 8/22/2025 Approved BRENDAN MORELLI
Underground Mechanical 9/30/2025 Approved SABAS ALONSO
Wood Frame 9/30/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Partial Approval SABAS ALONSO
Insulation 10/2/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Partial Approval RONNIE MEDINA
Insulation 10/3/2025 Partial Inspection RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 10/28/2025 Conditional Approval SABAS ALONSO
Deputy Wood Construction 10/29/2025 Conditional Approval ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Approved SABAS ALONSO
Deputy Wood Construction 11/6/2025 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 11/14/2025 Approved SABAS ALONSO
HVAC-Rough 11/14/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 11/20/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 11/20/2025 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 11/21/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 11/21/2025 Approved SABAS ALONSO
Verify Sprinkler Sign Off 11/21/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/24/2025 Approved SABAS ALONSO
Green Building Rough 11/24/2025 Approved SABAS ALONSO
Insulation 12/1/2025 Approved SABAS ALONSO
Drywall Nailing 12/8/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 12/8/2025 Approved ANTHONY RAMOS
Sewer 1/13/2026 Approved SABAS ALONSO
Underground Mechanical 1/13/2026 Partial Approval SABAS ALONSO
ELECTRICAL-Final 3/10/2026 Approved SABAS ALONSO
HVAC-Final 3/10/2026 Not Ready for Inspection SABAS ALONSO
Final 3/23/2026 Not Ready for Inspection SABAS ALONSO
Gas Test 3/23/2026 Approved SABAS ALONSO
Green Building Final 3/23/2026 Approved SABAS ALONSO
HVAC-Final 3/23/2026 Approved SABAS ALONSO
PLUMBING-Final 3/23/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/23/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 3/23/2026 Approved SABAS ALONSO
Smoke Detectors 3/23/2026 Approved SABAS ALONSO
Final 3/27/2026 Corrections Issued SABAS ALONSO
Final 4/22/2026 OK to Issue CofO SABAS ALONSO