17236 W NORDHOFF ST 91325
Certificate Information: 17236 W NORDHOFF ST 91325
- Application / Permit
- 25010-10000-00296
- Plan Check / Job No.
- B25LA02481
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNITS PER GC 66323(a)(2)
- Permit Issued
- Issued on 8/18/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | KEVIN MORALES |
| Corrections Issued | 2/6/2025 | KEVIN MORALES |
| Quality Review Completed | 2/6/2025 | EUGENE BARBEAU |
| Building Plans Picked Up | 2/6/2025 | APPLICANT |
| Plan Check Approved | 8/13/2025 | KEVIN MORALES |
| Issued | 8/18/2025 | APPLICANT |
| CofO in Progress | 1/7/2026 | CHRISTOPHER ROJAS |
| CofO in Progress | 1/9/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 1/10/2026 | RUBEN SALAS |
| CofO Issued | 1/10/2026 | RUBEN SALAS |
| Permit Finaled | 1/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 3/17/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 3/17/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/22/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 9/2/2025 | Approved | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 9/4/2025 | Approved | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 9/4/2025 | Approved | NICHOLAS TROWBRIDGE |
| Deputy Wood Construction | 9/22/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/30/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 9/30/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 9/30/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 9/30/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Wood Frame | 9/30/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 10/15/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Sewer | 10/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 10/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 11/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Gas Test | 11/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 11/5/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 11/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 11/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 11/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 11/19/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Insulation | 11/21/2025 | Conditional Approval | KEVIN BERBERYAN |
| Drywall Nailing | 11/25/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/25/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 1/2/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/2/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/2/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 1/2/2026 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 1/2/2026 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 1/2/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 1/2/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 1/2/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Service/Power Release | 1/2/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/2/2026 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/6/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/6/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 1/6/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| HVAC-Final | 1/6/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 1/6/2026 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 1/6/2026 | Approved | CHRISTOPHER ROJAS |