17236 W NORDHOFF ST 91325

Certificate Information: 17236 W NORDHOFF ST 91325

Application / Permit
25010-10000-00296
Plan Check / Job No.
B25LA02481
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNITS PER GC 66323(a)(2)
Permit Issued
Issued on 8/18/2025
Issuing Office
Valley
Current Status
CofO Issued on 1/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 KEVIN MORALES
Corrections Issued 2/6/2025 KEVIN MORALES
Quality Review Completed 2/6/2025 EUGENE BARBEAU
Building Plans Picked Up 2/6/2025 APPLICANT
Plan Check Approved 8/13/2025 KEVIN MORALES
Issued 8/18/2025 APPLICANT
CofO in Progress 1/7/2026 CHRISTOPHER ROJAS
CofO in Progress 1/9/2026 CHRISTOPHER ROJAS
Permit Finaled 1/10/2026 RUBEN SALAS
CofO Issued 1/10/2026 RUBEN SALAS
Permit Finaled 1/10/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/17/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/17/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 3/17/2025 RYAN CASTRO
Sewer availability Cleared 3/17/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/22/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 9/2/2025 Approved NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 9/4/2025 Approved NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 9/4/2025 Approved NICHOLAS TROWBRIDGE
Deputy Wood Construction 9/22/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 9/30/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 9/30/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 9/30/2025 Corrections Issued NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 9/30/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Wood Frame 9/30/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 10/15/2025 Corrections Issued NICHOLAS TROWBRIDGE
Sewer 10/15/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 10/15/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 11/5/2025 Approved NICHOLAS TROWBRIDGE
Gas Test 11/5/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 11/5/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 11/5/2025 Approved NICHOLAS TROWBRIDGE
Shower Pan 11/5/2025 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 11/5/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 11/19/2025 Partial Approval NICHOLAS TROWBRIDGE
Insulation 11/21/2025 Conditional Approval KEVIN BERBERYAN
Drywall Nailing 11/25/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 11/25/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 1/2/2026 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 1/2/2026 Corrections Issued CHRISTOPHER ROJAS
Final 1/2/2026 Corrections Issued CHRISTOPHER ROJAS
Gas Test 1/2/2026 Approved CHRISTOPHER ROJAS
Green Building Final 1/2/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 1/2/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 1/2/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 1/2/2026 Corrections Issued CHRISTOPHER ROJAS
Service/Power Release 1/2/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 1/2/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/6/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 1/6/2026 Approved CHRISTOPHER ROJAS
Final 1/6/2026 OK to Issue CofO CHRISTOPHER ROJAS
HVAC-Final 1/6/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 1/6/2026 Approved CHRISTOPHER ROJAS
Service/Power Release 1/6/2026 Approved CHRISTOPHER ROJAS