8779 S HOBART BLVD 90047
Certificate Information: 8779 S HOBART BLVD 90047
- Application / Permit
- 25010-10000-00256
- Plan Check / Job No.
- B25LA02112
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SFD PER TYPE WFPP W/ NFPA 13D SPRINKLERS
- Permit Issued
- Issued on 2/20/2025
- Issuing Office
- Current Status
- CofO Issued on 8/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | HERNAN ARREOLA |
| Corrections Issued | 1/27/2025 | HERNAN ARREOLA |
| Quality Review Completed | 1/31/2025 | KEN GILL |
| Building Plans Picked Up | 1/31/2025 | APPLICANT |
| Plan Check Approved | 2/20/2025 | HERNAN ARREOLA |
| Issued | 2/20/2025 | APPLICANT |
| CofO in Progress | 8/11/2025 | MICHAEL LEWIS |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
| CofO Issued | 8/12/2025 | DEROLD HAUFF |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2025 | DAVID VO |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2025 | DAVID VO |
| Roof/Waste drainage to street | Cleared | 2/6/2025 | DAVID VO |
| Sewer availability | Cleared | 2/6/2025 | DAVID VO |
| Hydrant and Access approval | Cleared | 2/10/2025 | PATRICK PEREZ |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/7/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 3/7/2025 | Not Ready for Inspection | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/24/2025 | Partial Approval | JOSE MACIAS |
| Underground Mechanical | 3/24/2025 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 3/25/2025 | Approved | JOSE MACIAS |
| Insulation | 3/27/2025 | Approved | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Partial Approval | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Approved | WAYNE REGESTER |
| Rough-Elec/Plmb/HVAC | 5/6/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 5/8/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Rough | 5/8/2025 | Corrections Issued | WAYNE REGESTER |
| Interior/Exterior Lathing | 5/8/2025 | Corrections Issued | WAYNE REGESTER |
| Verify Sprinkler Sign Off | 5/8/2025 | Not Ready for Inspection | WAYNE REGESTER |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | MICHAEL LEWIS |
| Green Building Rough | 5/9/2025 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/9/2025 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 5/9/2025 | Approved | MICHAEL LEWIS |
| Insulation | 5/14/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 5/20/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 5/27/2025 | Approved | WAYNE REGESTER |
| Sewer | 6/23/2025 | Approved | WAYNE REGESTER |
| Underground Mechanical | 6/23/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 8/1/2025 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 8/1/2025 | Approved | WAYNE REGESTER |
| Green Building Final | 8/1/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV Not Required | WAYNE REGESTER |
| Service/Power Release | 8/1/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 8/1/2025 | Approved | WAYNE REGESTER |
| Pre-Inspection | 8/4/2025 | Approved | WAYNE REGESTER |
| Final | 8/7/2025 | OK to Issue CofO | WAYNE REGESTER |