702 N OCCIDENTAL BLVD 90026

Certificate Information: 702 N OCCIDENTAL BLVD 90026

Application / Permit
25010-10000-00255
Plan Check / Job No.
B25LA02096
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] New 2 story SFD, 2400 sq ft,
Permit Issued
Issued on 7/21/2025
Issuing Office
Current Status
Issued on 7/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/21/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 SALVADOR QUINTANILLA
Corrections Issued 1/25/2025 SALVADOR QUINTANILLA
Quality Review Completed 1/27/2025 PETER KIM
Applicant returned to address corrections 5/5/2025 SALVADOR QUINTANILLA
Applicant returned to address corrections 5/23/2025 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/2/2025 SALVADOR QUINTANILLA
Plan Check Approved 6/12/2025 SALVADOR QUINTANILLA
Issued 7/21/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/3/2025 AMBER CAMPBELL
Highway dedication Cleared 2/3/2025 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 2/11/2025 AMBER CAMPBELL
Sewer availability Cleared 2/11/2025 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 3/12/2025 AMBER CAMPBELL
Frnt yard landscape/Water mgmt Cleared 4/8/2025 YINGSHI HUANG

Contact Information

Contractor Golden Point Construction; Lic. No.: 965193-B 731 EAST 75TH STREET      LOS ANGELES, CA 90001
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/22/2025 Partial Inspection FREDDIE RIVERA
Pre-Inspection 7/22/2025 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 8/22/2025 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 8/25/2025 Partial Approval FREDDIE RIVERA
METHANE-Barrier 8/25/2025 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 8/25/2025 Partial Inspection FREDDIE RIVERA
Pre-Inspection 8/25/2025 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 10/22/2025 Partial Approval FREDDIE RIVERA
Deputy Steel/Welding 10/29/2025 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/6/2025 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/7/2025 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/7/2025 Not Ready for Inspection HAMIK HARTOUNIAN
METHANE-Barrier 11/7/2025 Not Ready for Inspection HAMIK HARTOUNIAN
METHANE-Subgrade 11/7/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Other (see comments) 11/10/2025 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/12/2025 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 12/18/2025 Partial Approval FREDDIE RIVERA
METHANE-Subgrade 1/13/2026 Approved FREDDIE RIVERA
METHANE-Barrier 1/21/2026 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 1/27/2026 Approved FREDDIE RIVERA
Footing/Foundation/Slab 1/27/2026 Approved FREDDIE RIVERA
ELECTRICAL-Rough 4/15/2026 Approved FREDDIE RIVERA
HVAC-Rough 4/15/2026 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 4/15/2026 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/17/2026 Corrections Issued FREDDIE RIVERA
HVAC-Rough 4/17/2026 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/24/2026 Partial Approval FREDDIE RIVERA
HVAC-Rough 4/24/2026 Approved FREDDIE RIVERA
METHANE-Rough 4/24/2026 Not Ready for Inspection FREDDIE RIVERA
Interior/Exterior Lathing 5/7/2026 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 5/7/2026 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 5/8/2026 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/11/2026 Partial Inspection FREDDIE RIVERA