13810 N ELDRIDGE AVE 91342
Certificate Information: 13810 N ELDRIDGE AVE 91342
- Application / Permit
- 25010-10000-00252
- Plan Check / Job No.
- B25LA02092
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1-STORY RESIDENCE PER SB9 NFPA-13D FIRE SPRINKLERS THRU-OUT
- Permit Issued
- Issued on 6/13/2025
- Issuing Office
- Valley
- Current Status
- Issued on 6/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | JESSE VIDUYA |
| Corrections Issued | 2/6/2025 | JESSE VIDUYA |
| Quality Review Completed | 2/12/2025 | KEN GILL |
| Building Plans Picked Up | 2/20/2025 | APPLICANT |
| Plan Check Approved | 6/6/2025 | JESSE VIDUYA |
| Issued | 6/13/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/26/2025 | OSCAR CASTRO |
| Address approval | Cleared | 3/11/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/11/2025 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 5/7/2025 | YINGSHI HUANG |
| Hydrant and Access approval | Cleared | 5/27/2025 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/3/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/21/2025 | Partial Inspection | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 10/9/2025 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 10/9/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/1/2025 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 12/1/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 12/1/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/3/2025 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 12/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 12/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 3/13/2026 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 3/13/2026 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 3/13/2026 | Partial Approval | KEVIN BERBERYAN |
| Insulation | 3/19/2026 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 3/19/2026 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 3/19/2026 | Approved | KEVIN BERBERYAN |
| Sewer | 3/19/2026 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 3/19/2026 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 3/24/2026 | Corrections Issued | DAVID SCANTLIN |
| Green Building Rough | 3/24/2026 | Approved | DAVID SCANTLIN |
| Shower Pan | 4/16/2026 | Approved | KEVIN BERBERYAN |