1116 1/4 E 113TH ST 90059

Certificate Information: 1116 1/4 E 113TH ST 90059

Application / Permit
25010-10000-00238
Plan Check / Job No.
B24LA37564
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New 2-Story Detached Accessory Dwelling unit PER LAMC 12.22 A.33(c) AND (d). Fire Sprinkler NFPA 13D
Permit Issued
Issued on 2/13/2025
Issuing Office
Current Status
CofO Issued on 11/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/25/2024 APPLICANT
Assigned to Plan Check Engineer 1/9/2025 KHEDER ALRAZAA
Corrections Issued 1/20/2025 KHEDER ALRAZAA
Quality Review Completed 1/22/2025 GARO TELMI
Plan Check Approved 2/12/2025 KHEDER ALRAZAA
Issued 2/13/2025 APPLICANT
CofO in Progress 10/28/2025 ANTHONY EGSON
Permit Finaled 11/14/2025 ANSON MAGLASANG
CofO Issued 11/14/2025 ANSON MAGLASANG
Permit Finaled 11/14/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/22/2025 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 1/27/2025 JESSICA OPINION
Roof/Waste drainage to street Cleared 1/27/2025 JESSICA OPINION
Sewer availability Cleared 1/27/2025 JESSICA OPINION

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/19/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 2/19/2025 Not Ready for Inspection ANTHONY EGSON
Underground Mechanical 2/19/2025 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 2/26/2025 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 4/24/2025 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Partial Approval ANTHONY EGSON
Deputy Wood Construction 4/30/2025 Conditional Approval ANTHONY EGSON
ELECTRICAL-Rough 6/9/2025 Approved ANTHONY EGSON
HVAC-Rough 6/9/2025 Approved ANTHONY EGSON
PLUMBING-Rough 6/9/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 6/10/2025 Approved ANTHONY EGSON
Green Building Rough 6/10/2025 Approved ANTHONY EGSON
Verify Sprinkler Sign Off 6/10/2025 Approved ANTHONY EGSON
Insulation 6/16/2025 Approved ANTHONY EGSON
Drywall Nailing 6/23/2025 Approved JOHN KLARIN
Interior/Exterior Lathing 6/23/2025 Approved JOHN KLARIN
Sewer 8/4/2025 Approved ANTHONY EGSON
Underground Mechanical 8/4/2025 Not Ready for Inspection ANTHONY EGSON
Gas Test 8/5/2025 Not Ready for Inspection ANTHONY EGSON
Underground Mechanical 8/5/2025 Not Ready for Inspection ANTHONY EGSON
Underground Mechanical 8/11/2025 Not Ready for Inspection ANTHONY EGSON
Verify Rec and Parks Fee Memo 8/11/2025 Not Ready for Inspection ANTHONY EGSON
Underground Mechanical 8/18/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 9/23/2025 Corrections Issued ANTHONY EGSON
HVAC-Final 9/23/2025 Corrections Issued ANTHONY EGSON
Smoke Detectors 9/23/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 9/30/2025 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 9/30/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 9/30/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 10/6/2025 Approved ANTHONY EGSON
Green Building Final 10/6/2025 Approved ANTHONY EGSON
HVAC-Final 10/6/2025 Corrections Issued ANTHONY EGSON
Service/Power Release 10/6/2025 Approved ANTHONY EGSON
Final 10/27/2025 OK to Issue CofO ANTHONY EGSON
HVAC-Final 10/27/2025 Approved ANTHONY EGSON
PLUMBING-Final 10/27/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/27/2025 SGSOV Approved ANTHONY EGSON