1801-1803 E 107TH ST 90002
Certificate Information: 1801-1803 E 107TH ST 90002
- Application / Permit
- 25010-10000-00235
- Plan Check / Job No.
- B25LA01903
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN. NEW 2-STORY DUPLEX W/ ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 8/7/2025
- Issuing Office
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | ARSALAN SHABESTARI |
| Corrections Issued | 1/27/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/4/2025 | PRANITA SHAH |
| Plan Check Approved | 7/12/2025 | ARSALAN SHABESTARI |
| Issued | 8/7/2025 | APPLICANT |
| CofO in Progress | 3/11/2026 | ARTHUR NEGRETE |
| Permit Finaled | 4/7/2026 | ANSON MAGLASANG |
| CofO Issued | 4/7/2026 | ANSON MAGLASANG |
| Permit Finaled | 4/7/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/15/2025 | JERRY KAO |
| Low Impact Development (LID) | Cleared | 2/20/2025 | SARAH YOUSSEF |
| Address approval | Cleared | 2/21/2025 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 2/21/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 2/25/2025 | TAL SHEMEN |
| SB8 RUD | Cleared | 6/27/2025 | SAMANTHA RIVERA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/10/2025 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/10/2025 | Approved | ANTHONY EGSON |
| Sewer | 10/8/2025 | Approved | ANTHONY EGSON |
| Underground Mechanical | 10/8/2025 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 10/8/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 10/9/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 11/26/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 12/31/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 12/31/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 1/6/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 1/6/2026 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 1/6/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 1/6/2026 | Approved | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 1/6/2026 | Approved | ARTHUR NEGRETE |
| Insulation | 1/9/2026 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 1/20/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 1/20/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 3/3/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 3/3/2026 | Approved | ARTHUR NEGRETE |
| Final | 3/4/2026 | Partial Approval | ARTHUR NEGRETE |
| Green Building Final | 3/4/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 3/4/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 3/4/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/4/2026 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 3/4/2026 | Approved | ARTHUR NEGRETE |
| Final | 3/10/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| HVAC-Final | 3/10/2026 | Approved | ARTHUR NEGRETE |