1801-1803 E 107TH ST 90002

Certificate Information: 1801-1803 E 107TH ST 90002

Application / Permit
25010-10000-00235
Plan Check / Job No.
B25LA01903
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN. NEW 2-STORY DUPLEX W/ ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 8/7/2025
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 ARSALAN SHABESTARI
Corrections Issued 1/27/2025 ARSALAN SHABESTARI
Quality Review Completed 2/4/2025 PRANITA SHAH
Plan Check Approved 7/12/2025 ARSALAN SHABESTARI
Issued 8/7/2025 APPLICANT
CofO in Progress 3/11/2026 ARTHUR NEGRETE
Permit Finaled 4/7/2026 ANSON MAGLASANG
CofO Issued 4/7/2026 ANSON MAGLASANG
Permit Finaled 4/7/2026 ANSON MAGLASANG

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/15/2025 JERRY KAO
Low Impact Development (LID) Cleared 2/20/2025 SARAH YOUSSEF
Address approval Cleared 2/21/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 2/21/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 2/25/2025 TAL SHEMEN
Sewer availability Cleared 2/25/2025 TAL SHEMEN
SB8 RUD Cleared 6/27/2025 SAMANTHA RIVERA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B       ,
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/10/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 9/10/2025 Approved ANTHONY EGSON
Sewer 10/8/2025 Approved ANTHONY EGSON
Underground Mechanical 10/8/2025 Partial Approval ANTHONY EGSON
Wood Frame 10/8/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Not Ready for Inspection ANTHONY EGSON
Insulation 10/9/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/14/2025 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/26/2025 Approved ARTHUR NEGRETE
Rough-Elec/Plmb/HVAC 11/26/2025 Approved ARTHUR NEGRETE
HVAC-Rough 12/31/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 12/31/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 1/6/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 1/6/2026 Approved ARTHUR NEGRETE
Green Building Rough 1/6/2026 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 1/6/2026 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 1/6/2026 Approved ARTHUR NEGRETE
Insulation 1/9/2026 Approved ARTHUR NEGRETE
Drywall Nailing 1/20/2026 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 1/20/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 3/3/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 3/3/2026 Approved ARTHUR NEGRETE
Final 3/4/2026 Partial Approval ARTHUR NEGRETE
Green Building Final 3/4/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 3/4/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 3/4/2026 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 3/4/2026 Approved ARTHUR NEGRETE
Smoke Detectors 3/4/2026 Approved ARTHUR NEGRETE
Final 3/10/2026 OK to Issue CofO ARTHUR NEGRETE
HVAC-Final 3/10/2026 Approved ARTHUR NEGRETE