1824 W 43RD ST 90062
Certificate Information: 1824 W 43RD ST 90062
- Application / Permit
- 25010-10000-00221
- Plan Check / Job No.
- B25LA01842
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- CONVERSION OF EXISTING 18'-1" X 20'-2" GARAGE TO STORAGE SHED
- Permit Issued
- Issued on 2/20/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | LUKE GONZALES |
| Corrections Issued | 1/25/2025 | LUKE GONZALES |
| Building Plans Picked Up | 1/28/2025 | APPLICANT |
| Applicant returned to address corrections | 2/6/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 2/7/2025 | JOHN MESIAS |
| Plan Check Approved | 2/10/2025 | CRYSTEL MAALOUF |
| Issued | 2/20/2025 | APPLICANT |
| CofO in Progress | 12/22/2025 | SABAS ALONSO |
| No Progress | 12/23/2025 | SABAS ALONSO |
| No Progress | 1/5/2026 | DEROLD HAUFF |
| CofO in Progress | 1/5/2026 | DEROLD HAUFF |
| Permit Finaled | 1/13/2026 | DEROLD HAUFF |
| Permit Finaled | 1/13/2026 | DEROLD HAUFF |
| CofO Issued | 1/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/30/2025 | DAVID VO |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2025 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Rupert Repairs Inc; Lic. No.: 997462-B | 708 N EUCALYPTUS AVE UNIT 102 INGLEWOOD, CA 90302 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/24/2025 | Partial Inspection | SABAS ALONSO |
| Underground Mechanical | 3/20/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 3/28/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/2/2025 | Conditional Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Partial Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 8/22/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 10/7/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 10/7/2025 | Approved | SABAS ALONSO |
| Sewer | 10/7/2025 | Approved | SABAS ALONSO |
| Insulation | 10/9/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 12/11/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| Drywall Nailing | 12/17/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 12/17/2025 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/17/2025 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 12/17/2025 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 12/19/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 12/19/2025 | OK to Issue CofO | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 12/19/2025 | Approved | SABAS ALONSO |