1824 W 43RD ST 90062

Certificate Information: 1824 W 43RD ST 90062

Application / Permit
25010-10000-00221
Plan Check / Job No.
B25LA01842
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
CONVERSION OF EXISTING 18'-1" X 20'-2" GARAGE TO STORAGE SHED
Permit Issued
Issued on 2/20/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 LUKE GONZALES
Corrections Issued 1/25/2025 LUKE GONZALES
Building Plans Picked Up 1/28/2025 APPLICANT
Applicant returned to address corrections 2/6/2025 SUNMIN LEE
Applicant returned to address corrections 2/7/2025 JOHN MESIAS
Plan Check Approved 2/10/2025 CRYSTEL MAALOUF
Issued 2/20/2025 APPLICANT
CofO in Progress 12/22/2025 SABAS ALONSO
No Progress 12/23/2025 SABAS ALONSO
No Progress 1/5/2026 DEROLD HAUFF
CofO in Progress 1/5/2026 DEROLD HAUFF
Permit Finaled 1/13/2026 DEROLD HAUFF
Permit Finaled 1/13/2026 DEROLD HAUFF
CofO Issued 1/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/30/2025 DAVID VO
Eng Process Fee Ord 176,300 Cleared 2/10/2025 ADRIAN SANCHEZ

Contact Information

Contractor Rupert Repairs Inc; Lic. No.: 997462-B 708 N EUCALYPTUS AVE UNIT 102      INGLEWOOD, CA 90302
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/24/2025 Partial Inspection SABAS ALONSO
Underground Mechanical 3/20/2025 Approved SABAS ALONSO
Footing/Foundation/Slab 3/28/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 7/2/2025 Conditional Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval LUIS CASTRO
Interior/Exterior Lathing 8/22/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 10/7/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 10/7/2025 Approved SABAS ALONSO
Sewer 10/7/2025 Approved SABAS ALONSO
Insulation 10/9/2025 Approved DEVON JACKSON
Drywall Nailing 12/11/2025 Not Ready for Inspection ANTHONY RAMOS
Drywall Nailing 12/17/2025 Not Ready for Inspection SABAS ALONSO
Final 12/17/2025 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 12/17/2025 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 12/19/2025 Not Ready for Inspection SABAS ALONSO
Final 12/19/2025 OK to Issue CofO SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 12/19/2025 Approved SABAS ALONSO