15235 W RUNNYMEDE ST 91405
Certificate Information: 15235 W RUNNYMEDE ST 91405
- Application / Permit
- 25010-10000-00179
- Plan Check / Job No.
- B25LA01575
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- NEW DETACHED 2-CAR CARPORT AT MIDDLE OF LOT
- Permit Issued
- Issued on 9/3/2025
- Issuing Office
- Valley
- Current Status
- Issued on 9/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | JAD BASMA |
| Corrections Issued | 1/25/2025 | JAD BASMA |
| Quality Review Completed | 1/29/2025 | KEN GILL |
| Building Plans Picked Up | 2/3/2025 | APPLICANT |
| Applicant returned to address corrections | 7/2/2025 | JAD BASMA |
| Plan Check Approved | 8/21/2025 | JAD BASMA |
| Issued | 9/3/2025 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 5/19/2025 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/28/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/5/2025 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 10/15/2025 | Not Ready for Inspection | DAVID MATSON |
| Footing/Foundation/Slab | 10/15/2025 | Not Ready for Inspection | DAVID MATSON |
| Underground Mechanical | 10/15/2025 | Not Ready for Inspection | DAVID MATSON |
| Underground Mechanical | 10/23/2025 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/5/2025 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 11/5/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 11/5/2025 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 11/10/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Steel/Welding | 11/26/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 12/8/2025 | Conditional Approval | RAUL OLAGI |
| Wood Frame | 12/9/2025 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/26/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/26/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/26/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/26/2026 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/26/2026 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 2/26/2026 | Approved | VINCENT HANLEY |
| Wood Frame | 2/26/2026 | Approved | VINCENT HANLEY |
| Insulation | 3/27/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/27/2026 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/7/2026 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/4/2026 | Partial Approval | JAVIER RAMOS JR |
| Gas Test | 5/18/2026 | Approved | OGANES TARAKHCHYAN |
| Grounding or Bonding | 5/18/2026 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/18/2026 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 6/10/2026 | Approved | OGANES TARAKHCHYAN |