149 N BRISTOL AVE 90049

Certificate Information: 149 N BRISTOL AVE 90049

Application / Permit
25010-10000-00078
Plan Check / Job No.
B24LA38373
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 33'-5 1/2" X 13'-5 3/4" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1) AND COVERED PORCH PER ENGINEER.
Permit Issued
Issued on 3/17/2025
Issuing Office
Current Status
Issued on 3/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/7/2025 APPLICANT
Assigned to Plan Check Engineer 1/10/2025 DANIEL ABRAMYAN
Corrections Issued 2/18/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 2/27/2025 GIOVANNY CHAVEZ
Plan Check Approved 3/4/2025 GIOVANNY CHAVEZ
Issued 3/17/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/13/2025 DANIEL ABRAMYAN
Address approval Cleared 2/12/2025 LIAM ODONOVAN
Sewer availability Cleared 2/12/2025 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 2/14/2025 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 2/14/2025 LIAM ODONOVAN

Contact Information

Architect Schierbeek,, Jefferson John; Lic. No.: NA22018       ,
Contractor Mccauley Design & Building Inc; Lic. No.: 994795-B       ,
Engineer Howe,, Carl William; Lic. No.: NA44773       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/6/2025 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 5/12/2025 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 5/12/2025 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 5/22/2025 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Approved BOBBY KEY
Sewer 3/12/2026 Approved KEVIN SARGSYAN
Underground Mechanical 3/12/2026 Approved KEVIN SARGSYAN
HVAC-Rough 3/13/2026 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 3/13/2026 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 4/3/2026 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 5/7/2026 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 5/7/2026 Approved KEVIN SARGSYAN