13772 W NURMI ST 91342
Certificate Information: 13772 W NURMI ST 91342
- Application / Permit
- 25010-10000-00071
- Plan Check / Job No.
- B25LA00408
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU per LAMC 12.22A.33(b)(1)
- Permit Issued
- Issued on 5/29/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2025 | MARCELA FRANQUEZ |
| Corrections Issued | 1/11/2025 | MARCELA FRANQUEZ |
| Quality Review Completed | 1/17/2025 | KEN GILL |
| Building Plans Picked Up | 1/21/2025 | APPLICANT |
| Plan Check Approved | 2/6/2025 | MARCELA FRANQUEZ |
| Issued | 5/29/2025 | APPLICANT |
| CofO in Progress | 5/12/2026 | JOSE AVILA |
| Permit Finaled | 5/18/2026 | RUBEN SALAS |
| CofO Issued | 5/18/2026 | RUBEN SALAS |
| Permit Finaled | 5/18/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/27/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 1/27/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Ada Restoration Inc; Lic. No.: 1103746-B | 19420 BUSINESS CENTER DR NORTHRIDGE, CA 91324 |
| Engineer | Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 | PO BOX 5044 PASADENA, CA 91117 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/10/2025 | Approved | KEVIN BERBERYAN |
| Sewer | 6/10/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 6/10/2025 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 6/13/2025 | Corrections Issued | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 6/17/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Partial Inspection | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Corrections Issued | KEVIN BERBERYAN |
| Wood Frame | 7/21/2025 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 8/11/2025 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 8/11/2025 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 8/11/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/13/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 8/18/2025 | Corrections Issued | KEVIN BERBERYAN |
| Drywall Nailing | 8/22/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 8/22/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 9/2/2025 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 9/2/2025 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 1/27/2026 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 1/27/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 1/27/2026 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 1/27/2026 | Approved | KEVIN BERBERYAN |
| Green Building Final | 1/27/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 1/27/2026 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 1/27/2026 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV No Gas | KEVIN BERBERYAN |
| Service/Power Release | 1/27/2026 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 1/27/2026 | Approved | KEVIN BERBERYAN |
| Final | 2/2/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 2/2/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 2/3/2026 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 2/3/2026 | Approved | KEVIN BERBERYAN |