3619 W ELLSWORTH ST 90026
Certificate Information: 3619 W ELLSWORTH ST 90026
- Application / Permit
- 25010-10000-00024
- Plan Check / Job No.
- B25LA00122
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 1 story ADU per GC 66323(a)(2).
- Permit Issued
- Issued on 6/25/2025
- Issuing Office
- Current Status
- Issued on 6/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | MARCELA FRANQUEZ |
| Corrections Issued | 1/27/2025 | MARCELA FRANQUEZ |
| Quality Review Completed | 1/31/2025 | KEN GILL |
| Building Plans Picked Up | 2/3/2025 | APPLICANT |
| Plan Check Approved | 4/17/2025 | MARCELA FRANQUEZ |
| Issued | 6/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2025 | PAMELA TENEZA |
| Roof/Waste drainage to street | Cleared | 2/1/2025 | TAL SHEMEN |
| Hydrant and Access approval | Cleared | 2/18/2025 | JERRY KAO |
| Disturb/Remove Protected Trees | Cleared | 2/27/2025 | MIGUEL ORNELAS |
| Sewer availability | Cleared | 3/22/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2025 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 4/17/2025 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Gross Design & Build Inc; Lic. No.: 1079184-B | 928 N SAN FERNANDO BLVD STE J213 BURBANK, CA 91504 |
| Engineer | Khanjian,, John Hovik; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
| Engineer | Nalbandian,, Serop Krekor; Lic. No.: M39801 | 1236 N COLUMBUS AVE UNIT 4 GLENDALE, CA 91202 |
| Engineer | Zlotnik,, Alexander; Lic. No.: C69417 | 11323 PASEO LA CUMBRE PORTER RANCH, CA 91326 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/25/2025 | Conditional Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 7/31/2025 | Corrections Issued | FREDDIE RIVERA |
| Sewer | 7/31/2025 | Partial Inspection | FREDDIE RIVERA |
| Underground Mechanical | 7/31/2025 | Partial Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 9/16/2025 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/16/2025 | Partial Inspection | FREDDIE RIVERA |
| Sewer | 9/16/2025 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 9/16/2025 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 9/30/2025 | Partial Approval | FREDDIE RIVERA |
| Masonry Wall/Backfill | 9/30/2025 | Partial Inspection | FREDDIE RIVERA |
| Masonry Wall/Backfill | 10/6/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 10/6/2025 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 10/16/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/21/2026 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2026 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 1/21/2026 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/4/2026 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/4/2026 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 2/4/2026 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/4/2026 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 2/4/2026 | Approved | FREDDIE RIVERA |
| Insulation | 2/11/2026 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 2/11/2026 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 3/12/2026 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/12/2026 | Approved | FREDDIE RIVERA |