1033 N ROSCOMARE ROAD 90077
Certificate Information: 1033 N ROSCOMARE ROAD 90077
- Application / Permit
- 24047-40000-00738
- Plan Check / Job No.
- B24SP00106
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ALTERATION TO EXISTING IN-GROUND SWIMMING POOL TO ADD SPA AND BAJA SHELF, WITHIN EXISTING POOL SHELL AND REDUCE MAX DEPTH TO 5', PER STANDARD PLAN 268, AND ADDITIONAL DETAILS.
- Permit Issued
- Issued on 5/31/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | SERGIO SILVA |
| Corrections Issued | 5/30/2024 | SERGIO SILVA |
| Issued | 5/31/2024 | APPLICANT |
| CofO in Progress | 2/13/2025 | CARLOS MATAMOROS |
| Permit Finaled | 2/20/2025 | RICHARD STEINBACH |
| CofO Issued | 2/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Rodcrete C Development; Lic. No.: 842017-C53 | 8482 HOLDER ST BUENA PARK, CA 90620 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 6/4/2024 | Approved | STEPHANIE SWANSON |
| Pre-Gunite | 6/4/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 6/5/2024 | Conditional Approval | MICHAEL PELHAM |
| Grounding or Bonding | 6/6/2024 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 6/6/2024 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 6/20/2024 | Corrections Issued | CARLOS MATAMOROS |
| Grounding or Bonding | 6/24/2024 | Partial Approval | CARLOS MATAMOROS |
| Deck | 6/27/2024 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 8/21/2024 | Corrections Issued | CARLOS MATAMOROS |
| Enclosure/Fence | 8/29/2024 | Approved | CARLOS MATAMOROS |
| Final | 9/30/2024 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/30/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Final | 1/31/2025 | Corrections Issued | CARLOS MATAMOROS |
| Final | 2/11/2025 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Final | 2/13/2025 | Approved | CARLOS MATAMOROS |
| Final | 2/13/2025 | OK to Issue CofO | CARLOS MATAMOROS |
| PLUMBING-Final | 2/13/2025 | Approved | CARLOS MATAMOROS |