811 N MAJORCA PL 90049
Certificate Information: 811 N MAJORCA PL 90049
- Application / Permit
- 24047-30000-01680
- Plan Check / Job No.
- B24WL09343
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL AND SPA PER STD PLAN#265 AND ENGINEER'S CALCULATIONS 1 OF 2
- Permit Issued
- Issued on 2/20/2025
- Issuing Office
- Current Status
- CofO Issued on 2/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | ALFREDO JARA |
| Corrections Issued | 12/1/2024 | ALFREDO JARA |
| Building Plans Picked Up | 12/5/2024 | APPLICANT |
| Applicant returned to address corrections | 12/18/2024 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 12/31/2024 | JOHNPAUL ISIP |
| Issued | 2/20/2025 | APPLICANT |
| CofO in Progress | 2/4/2026 | EVAN COOPER |
| Permit Finaled | 2/5/2026 | RICHARD STEINBACH |
| CofO Issued | 2/5/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/5/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/31/2024 | VASIL MIHALEV |
Contact Information
| Contractor | Baraca Remodeling Inc; Lic. No.: 1072805-B | 23185 LA CADENA DRIVE #104 LAGUNA HILLS, CA 92653 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/25/2025 | Corrections Issued | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 2/25/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grading Pre-Inspection | 2/25/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Gunite | 2/25/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Rough-Plumbing | 2/25/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 2/26/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grading Pre-Inspection | 2/26/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 2/26/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pool Piping | 2/26/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Inspection | 2/26/2025 | Corrections Issued | CARLOS MATAMOROS |
| Rough-Plumbing | 2/26/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 3/7/2025 | Approved | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 3/7/2025 | Approved | CARLOS MATAMOROS |
| Gunite | 3/7/2025 | Approved | CARLOS MATAMOROS |
| Pool Piping | 3/7/2025 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 3/7/2025 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 3/7/2025 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 3/10/2025 | Conditional Approval | CARLOS MATAMOROS |
| Grounding or Bonding | 6/16/2025 | Approved | MEL KHACHATOURIAN |
| Deck | 8/21/2025 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 8/21/2025 | Corrections Issued | CARLOS MATAMOROS |
| Enclosure/Fence | 9/22/2025 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 9/22/2025 | Corrections Issued | CARLOS MATAMOROS |
| Final | 9/30/2025 | Corrections Issued | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 9/30/2025 | Not Ready for Inspection | EUSEBIO GUZMAN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Not Required | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 10/24/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 10/30/2025 | Not Ready for Inspection | EUSEBIO GUZMAN |
| Final | 1/27/2026 | Corrections Issued | EVAN COOPER |
| Pool Equipment Noise Test | 1/29/2026 | Approved | EUSEBIO GUZMAN |
| Final | 2/3/2026 | Corrections Issued | EVAN COOPER |
| Final | 2/4/2026 | OK to Issue CofO | EVAN COOPER |