306 S ANITA AVE 90049
Certificate Information: 306 S ANITA AVE 90049
- Application / Permit
- 24047-30000-01143
- Plan Check / Job No.
- B24WL06382
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool & spa per std. plan #270
- Permit Issued
- Issued on 10/8/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2024 | YASHAR EMAMI |
| Corrections Issued | 8/27/2024 | YASHAR EMAMI |
| Building Plans Picked Up | 9/9/2024 | APPLICANT |
| Applicant returned to address corrections | 9/30/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 10/4/2024 | YASHAR EMAMI |
| Issued | 10/8/2024 | APPLICANT |
| CofO in Progress | 7/3/2025 | HERBERT GIRON |
| Permit Finaled | 7/8/2025 | RICHARD STEINBACH |
| CofO Issued | 7/8/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/8/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/30/2024 | YASHAR EMAMI |
Contact Information
| Contractor | Ke General Building Inc; Lic. No.: 1049318-B | 5227 PACIFIC AVENUE LONG BEACH, CA 90805 |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 10/28/2024 | Approved | JESUS RODRIGUEZ |
| Pre-Gunite | 10/28/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Pre-Gunite | 11/4/2024 | Approved | JESUS RODRIGUEZ |
| Deck | 12/24/2024 | Approved | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 5/27/2025 | Approved | JAMES VORHIS |
| Final | 6/2/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/2/2025 | SGSOV Not Ready | HERBERT GIRON |
| Final | 6/11/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/11/2025 | SGSOV Approved | HERBERT GIRON |
| Final | 6/16/2025 | Conditional Approval | HERBERT GIRON |
| Final | 7/3/2025 | OK to Issue CofO | HERBERT GIRON |