960 N CHANTILLY ROAD 90077

Certificate Information: 960 N CHANTILLY ROAD 90077

Application / Permit
24047-30000-00312
Plan Check / Job No.
B24WL00527
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
To reduce the size of (E) 16'x 32' pool to 9'-10" x 22'-10" at the rear of the lot.
Permit Issued
Issued on 3/21/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2024 APPLICANT
Assigned to Plan Check Engineer 3/8/2024 JAHANSHAH POURHASSAN
Corrections Issued 3/8/2024 JAHANSHAH POURHASSAN
Applicant returned to address corrections 3/13/2024 EDWIN ESPIN
Plan Check Approved 3/15/2024 ZENA HADDIS
Issued 3/21/2024 APPLICANT
CofO in Progress 5/13/2026 RYAN SALAZAR
Permit Finaled 5/13/2026 RICHARD STEINBACH
CofO Issued 5/13/2026 RICHARD STEINBACH
Permit Finaled 5/13/2026 RICHARD STEINBACH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Boswell Construction Inc; Lic. No.: 934480-B 14611 VENTURA BLVD 2ND FLOOR      SHERMAN OAKS, CA 91403
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

ANDREW NAVE, (310) 914-3908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/3/2024 Corrections Issued MICHAEL PELHAM
Special/Order Compliance 4/3/2024 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 5/3/2024 Corrections Issued MICHAEL PELHAM
Pre-Inspection 3/9/2026 Corrections Issued ANDREW NAVE
Special/Order Compliance 3/9/2026 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 3/23/2026 Partial Inspection CHRISTOPHER WILSON
Enclosure/Fence 3/25/2026 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 3/26/2026 Corrections Issued CHRISTOPHER WILSON
Enclosure/Fence 4/22/2026 Corrections Issued CHRISTOPHER WILSON
Final 5/6/2026 Corrections Issued RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Approved RYAN SALAZAR
Final 5/11/2026 OK to Issue CofO RYAN SALAZAR