2361 N STANLEY HILLS DR 90046
Certificate Information: 2361 N STANLEY HILLS DR 90046
- Application / Permit
- 24047-20000-01826
- Plan Check / Job No.
- B24VN26805
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 12'0"X30'8" POOL & SPA WITH CATCH BASIN ON PILES PER ENGINEERED DESIGN
- Permit Issued
- Issued on 6/26/2025
- Issuing Office
- Valley
- Current Status
- Issued on 6/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2025 | MARVEL DELACRUZ |
| Corrections Issued | 1/17/2025 | MARVEL DELACRUZ |
| Quality Review Completed | 1/23/2025 | RARES BODEA |
| Building Plans Picked Up | 1/24/2025 | APPLICANT |
| Applicant returned to address corrections | 3/28/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 4/25/2025 | MARVEL DELACRUZ |
| Plan Check Approved | 6/26/2025 | MARVEL DELACRUZ |
| Issued | 6/26/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
| Geologist | Nguyen,, An; Lic. No.: EG2468 | 5913 SATURN STREET LOS ANGELES, CA 90035 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 2/5/2026 | Corrections Issued | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 3/24/2026 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 4/2/2026 | Not Ready for Inspection | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 4/9/2026 | Corrections Issued | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 4/14/2026 | Not Ready for Inspection | ROY SPAULDING |
| Pre-Inspection | 4/16/2026 | Corrections Issued | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 4/21/2026 | Corrections Issued | ROY SPAULDING |
| Special/Order Compliance | 4/21/2026 | Partial Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/24/2026 | Partial Approval | BRENDAN MORELLI |
| Pool Piping | 6/24/2026 | Approved | BRENDAN MORELLI |
| Rough-Electrical | 6/24/2026 | Approved | BRENDAN MORELLI |
| Rough-Plumbing | 6/24/2026 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 6/25/2026 | Corrections Issued | BRENDAN MORELLI |