2361 N STANLEY HILLS DR 90046

Certificate Information: 2361 N STANLEY HILLS DR 90046

Application / Permit
24047-20000-01826
Plan Check / Job No.
B24VN26805
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) 12'0"X30'8" POOL & SPA WITH CATCH BASIN ON PILES PER ENGINEERED DESIGN
Permit Issued
Issued on 6/26/2025
Issuing Office
Valley
Current Status
Issued on 6/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/26/2024 APPLICANT
Assigned to Plan Check Engineer 1/9/2025 MARVEL DELACRUZ
Corrections Issued 1/17/2025 MARVEL DELACRUZ
Quality Review Completed 1/23/2025 RARES BODEA
Building Plans Picked Up 1/24/2025 APPLICANT
Applicant returned to address corrections 3/28/2025 MARVEL DELACRUZ
Applicant returned to address corrections 4/25/2025 MARVEL DELACRUZ
Plan Check Approved 6/26/2025 MARVEL DELACRUZ
Issued 6/26/2025 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Rowlands,, James; Lic. No.: GE740 10954 SANTA MONICA BLVD      LOS ANGELES, CA 90025
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403
Geologist Nguyen,, An; Lic. No.: EG2468 5913 SATURN STREET      LOS ANGELES, CA 90035

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 2/5/2026 Corrections Issued ROY SPAULDING
Excavation/Setback/Form/Re-Bar 3/24/2026 Partial Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 4/2/2026 Not Ready for Inspection ROY SPAULDING
Excavation/Setback/Form/Re-Bar 4/9/2026 Corrections Issued ROY SPAULDING
Excavation/Setback/Form/Re-Bar 4/14/2026 Not Ready for Inspection ROY SPAULDING
Pre-Inspection 4/16/2026 Corrections Issued ROY SPAULDING
Excavation/Setback/Form/Re-Bar 4/21/2026 Corrections Issued ROY SPAULDING
Special/Order Compliance 4/21/2026 Partial Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/24/2026 Partial Approval BRENDAN MORELLI
Pool Piping 6/24/2026 Approved BRENDAN MORELLI
Rough-Electrical 6/24/2026 Approved BRENDAN MORELLI
Rough-Plumbing 6/24/2026 Approved BRENDAN MORELLI
Special/Order Compliance 6/25/2026 Corrections Issued BRENDAN MORELLI