6638 W LINDENHURST AVE 90048
Certificate Information: 6638 W LINDENHURST AVE 90048
- Application / Permit
- 24047-20000-01678
- Plan Check / Job No.
- B24VN24256
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14'-0" X 32'-0" POOL AND 14'-0" X 11'-0" SPA PER STD PLAN # 268 & ENGINEERING DETAILS.
- Permit Issued
- Issued on 1/7/2025
- Issuing Office
- Current Status
- CofO Issued on 8/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 12/9/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/10/2024 | APPLICANT |
| Issued | 1/7/2025 | APPLICANT |
| CofO in Progress | 8/25/2025 | EVAN COOPER |
| Permit Finaled | 8/27/2025 | RICHARD STEINBACH |
| CofO Issued | 8/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| CPC | Cleared | 12/26/2024 | JACQUELINE TORRES |
| Construction near power lines | Cleared | 1/6/2025 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 6/6/2025 | Partial Approval | EVAN COOPER |
| Enclosure/Fence | 7/21/2025 | Corrections Issued | EVAN COOPER |
| Enclosure/Fence | 8/4/2025 | Not Ready for Inspection | DANIEL VERA |
| Enclosure/Fence | 8/6/2025 | Partial Approval | EVAN COOPER |
| Equipment Noise Level | 8/14/2025 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Equipment Noise Level | 8/19/2025 | Approved | JUAN ESCOTO DELGADO |
| ELECTRICAL-Final | 8/20/2025 | Approved | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 8/20/2025 | Approved | MICHAEL ALLEN |
| Final | 8/20/2025 | Conditional Approval | MICHAEL ALLEN |
| Pre-Gunite | 8/20/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Not Required | MICHAEL ALLEN |
| Final | 8/25/2025 | OK to Issue CofO | EVAN COOPER |