441 N CROFT AVE 90048
Certificate Information: 441 N CROFT AVE 90048
- Application / Permit
- 24047-20000-01657
- Plan Check / Job No.
- B24VN23875
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20'-0"' X 25'-10" IRREGULAR SHAPED SWIMMING POOL WITH 7'-0"X12'-0" SPA PER LA CITY STANDARD PLAN #268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 1/2/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2024 | GURUNATH NESARAJAH |
| Corrections Issued | 11/22/2024 | GURUNATH NESARAJAH |
| Issued | 1/2/2025 | APPLICANT |
| CofO in Progress | 12/11/2025 | JOSH MEISTER |
| Permit Finaled | 12/13/2025 | DEROLD HAUFF |
| CofO Issued | 12/13/2025 | DEROLD HAUFF |
| Permit Finaled | 12/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/2/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 12/2/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Jr Pool & Spa Services; Lic. No.: 771197-D35 | P O BOX 5249 NORTH HOLLYWOOD, CA 91616 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 1/22/2025 | Approved | JOSE MACIAS |
| Pre-Gunite | 1/22/2025 | Approved | JOSE MACIAS |
| Deputy Shotcrete | 1/27/2025 | Conditional Approval | JOSE MACIAS |
| Grounding or Bonding | 3/4/2025 | Approved | JOSE MACIAS |
| Enclosure/Fence | 7/15/2025 | Corrections Issued | RONNIE MINDANAO |
| Enclosure/Fence | 7/17/2025 | Approved | BRENDAN MORELLI |
| Equipment Noise Level | 12/9/2025 | Approved | DA LIU |
| Excavation/Setback/Form/Re-Bar | 12/9/2025 | Approved | JOSH MEISTER |
| Final | 12/9/2025 | Corrections Issued | JOSH MEISTER |
| Pool Equipment Noise Test | 12/9/2025 | Approved | DA LIU |
| SGSOV-Seismic Gas S/O Valve | 12/9/2025 | SGSOV Not Ready | JOSH MEISTER |
| Final | 12/10/2025 | OK to Issue CofO | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Approved | JOSH MEISTER |