23026 W CALVERT ST 91367
Certificate Information: 23026 W CALVERT ST 91367
- Application / Permit
- 24047-20000-01626
- Plan Check / Job No.
- B24VN23526
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 33' X 18' POOL WITH 9'-6" X 9'-6" SPA INSIDE PER STANDARD PLAN 270 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 2/20/2025
- Issuing Office
- Current Status
- CofO Issued on 4/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | SELLA BENYAMIN |
| Corrections Issued | 12/12/2024 | SELLA BENYAMIN |
| Quality Review Completed | 12/13/2024 | STEVEN KIM |
| Building Plans Picked Up | 12/16/2024 | APPLICANT |
| Plan Check Approved | 2/20/2025 | SELLA BENYAMIN |
| Issued | 2/20/2025 | APPLICANT |
| CofO in Progress | 6/17/2025 | TROY SANDERS |
| Permit Finaled | 4/11/2026 | MICHAEL PELHAM |
| CofO Issued | 4/11/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/11/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/26/2025 | Not Ready for Inspection | TROY SANDERS |
| Deputy Shotcrete | 3/3/2025 | Conditional Approval | TROY SANDERS |
| Gas Piping or Gas Test | 3/17/2025 | Approved | TROY SANDERS |
| Pre-Gunite | 3/17/2025 | Approved | TROY SANDERS |
| Rough-Electrical | 3/17/2025 | Approved | TROY SANDERS |
| Rough-Plumbing | 3/17/2025 | Approved | TROY SANDERS |
| Pool Equipment Noise Test | 5/7/2025 | Approved | ALFREDO FLORES |
| Enclosure/Fence | 5/14/2025 | Approved | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 5/30/2025 | Approved | TROY SANDERS |
| Final | 5/30/2025 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Approved | TROY SANDERS |
| Final | 6/16/2025 | OK to Issue CofO | TROY SANDERS |