5117 N VINCENT AVE 90041

Certificate Information: 5117 N VINCENT AVE 90041

Application / Permit
24047-20000-01461
Plan Check / Job No.
B24VN20510
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 15'-0" X 9'-0" SWIMMING POOL AND 7'-0" X 9'-0" SPA PER LA CITY STANDARD PLAN #268.
Permit Issued
Issued on 11/21/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/22/2024 GIOVANNY CHAVEZ
Corrections Issued 10/22/2024 GIOVANNY CHAVEZ
Issued 11/21/2024 APPLICANT
CofO in Progress 4/9/2025 ALIZAH MAYAGOITIA
No Progress 4/13/2025 DEROLD HAUFF
CofO in Progress 4/13/2025 DEROLD HAUFF
CofO Issued 4/14/2025 DEROLD HAUFF
Permit Finaled 4/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/22/2024 GIOVANNY CHAVEZ

Contact Information

Contractor Westmod; Lic. No.: 1053685-C53 1276 E COLORADO BLVD STE 210      PASADENA, CA 91106
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 1/22/2025 Approved BRENDAN MORELLI
Pre-Gunite 1/22/2025 Partial Approval BRENDAN MORELLI
Deck 2/19/2025 Corrections Issued BRENDAN MORELLI
Deck 2/21/2025 Corrections Issued BRENDAN MORELLI
Deck 2/25/2025 Approved BRENDAN MORELLI
Enclosure/Fence 3/6/2025 Corrections Issued ALIZAH MAYAGOITIA
Special/Order Compliance 3/6/2025 Partial Approval DAVID WILLIAMS
Enclosure/Fence 3/17/2025 Corrections Issued BRENDAN MORELLI
Enclosure/Fence 3/19/2025 Approved DAVID WILLIAMS
Equipment Noise Level 4/3/2025 Approved ANDEY CHAPARRO
Pool Equipment Noise Test 4/3/2025 Approved ANDEY CHAPARRO
Excavation/Setback/Form/Re-Bar 4/4/2025 Approved ALIZAH MAYAGOITIA
Final 4/4/2025 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 4/4/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 4/4/2025 Approved ALIZAH MAYAGOITIA
Pre-Gunite 4/4/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Approved ALIZAH MAYAGOITIA
Final 4/8/2025 OK to Issue CofO ALIZAH MAYAGOITIA