15282 W GOLDEN CT 91342
Certificate Information: 15282 W GOLDEN CT 91342
- Application / Permit
- 24047-20000-01449
- Plan Check / Job No.
- B24VN20211
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED 32'X15' SWIMMING POOL W/ SPA PER CITY STD PLAN #268 W/ SUPPL ENGR DETAILS.
- Permit Issued
- Issued on 11/25/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 10/25/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 11/5/2024 | APPLICANT |
| Plan Check Approved | 11/22/2024 | DANIEL ABRAMYAN |
| Issued | 11/25/2024 | APPLICANT |
| CofO in Progress | 2/18/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 3/4/2025 | RUBEN SALAS |
| CofO Issued | 3/4/2025 | RUBEN SALAS |
| Permit Finaled | 3/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/21/2024 | CHARLES POWELL |
Contact Information
| Contractor | Out Of The Blue Pools Inc; Lic. No.: 1106756-B | 13953 RUNNYMEDE STREET VAN NUYS, CA 94105 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/9/2024 | Partial Approval | JENNIFER RABUCHIN |
| Pre-Gunite | 12/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Grounding or Bonding | 12/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Grounding or Bonding | 1/2/2025 | Approved | JENNIFER RABUCHIN |
| Enclosure/Fence | 1/13/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Enclosure/Fence | 1/15/2025 | Approved | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 2/12/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 2/12/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Pre-Gunite | 2/12/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Pool Equipment Noise Test | 2/14/2025 | Approved | FELIPE PENICHE |
| Final | 2/18/2025 | OK to Issue CofO | JENNIFER RABUCHIN |