15645 W COBALT ST 91342
Certificate Information: 15645 W COBALT ST 91342
- Application / Permit
- 24047-20000-01419
- Plan Check / Job No.
- B24VN19757
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 40' X 22' POOL WITH A 14' X 10' SPA AND 12' X 8' BAJA.
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Current Status
- CofO Issued on 5/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/15/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 11/21/2024 | YAQUB MIRZA |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 1/5/2026 | KEVIN BERBERYAN |
| CofO in Progress | 1/28/2026 | KEVIN BERBERYAN |
| CofO in Progress | 4/16/2026 | KEVIN BERBERYAN |
| CofO Issued | 5/21/2026 | RUBEN SALAS |
| Permit Finaled | 5/21/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/21/2024 | LUISANGEL VALENZUELA |
Contact Information
| Contractor | Martin - Ez - Pools; Lic. No.: 1024030-C53 | 7527 BALCOM AVENUE RESEDA, CA 91335 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Corrections Issued | KEVIN BERBERYAN |
| Rough-Electrical | 3/4/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Rough-Plumbing | 3/4/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 4/16/2025 | Approved | KEVIN BERBERYAN |
| Pool Piping | 4/16/2025 | Approved | KEVIN BERBERYAN |
| Enclosure/Fence | 7/9/2025 | Corrections Issued | KEVIN BERBERYAN |
| Enclosure/Fence | 7/15/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Enclosure/Fence | 7/17/2025 | Approved | KEVIN BERBERYAN |
| Grounding or Bonding | 7/17/2025 | Approved | KEVIN BERBERYAN |
| Deck | 8/20/2025 | Approved | KEVIN BERBERYAN |
| Grounding or Bonding | 9/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Equipment Noise Level | 9/24/2025 | Approved | FELIPE PENICHE |
| Final | 11/10/2025 | Corrections Issued | KEVIN BERBERYAN |
| Pre-Gunite | 11/10/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Final | 11/14/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Special/Order Compliance | 1/28/2026 | Corrections Issued | KEVIN BERBERYAN |
| Final | 4/16/2026 | OK to Issue CofO | KEVIN BERBERYAN |