4007 N DIXIE CANYON AVE 91423

Certificate Information: 4007 N DIXIE CANYON AVE 91423

Application / Permit
24047-20000-01375
Plan Check / Job No.
B24VN18937
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL WITH SPA PER LA CITY STANDARD PLAN #268.
Permit Issued
Issued on 5/8/2025
Issuing Office
Valley
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2024 APPLICANT
Assigned to Plan Check Engineer 10/7/2024 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/7/2024 SEWADA ZADOORIAN MILAGARDI
Issued 5/8/2025 APPLICANT
CofO in Progress 5/4/2026 MISAEL ESPARZA
CofO Issued 5/21/2026 RUBEN SALAS
Permit Finaled 5/21/2026 RUBEN SALAS

Permit Application Clearance Information

Tract Map conditions Cleared 2/3/2025 KATIE DEBIASE
Construction near power lines Cleared 2/12/2025 EDGAR PASCUA
Construction within easement Cleared 2/12/2025 EDGAR PASCUA
ZA Case Cleared 2/13/2025 JASON CHAN
Grading Pre-Inspection Cleared 5/6/2025 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Coastal Aquatic Creations; Lic. No.: 697943-C53 11730 GATEWAY BLVD      LOS ANGELES, CA 90064
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/8/2025 Corrections Issued MISAEL ESPARZA
Pre-Gunite 8/8/2025 Approved MISAEL ESPARZA
Rough-Electrical 8/8/2025 Approved MISAEL ESPARZA
Rough-Plumbing 8/8/2025 Approved MISAEL ESPARZA
Deck 2/18/2026 Corrections Issued NICHOLAS TROWBRIDGE
Enclosure/Fence 2/18/2026 Partial Approval NICHOLAS TROWBRIDGE
Pool Equipment Noise Test 2/26/2026 No Access for Inspection FELIPE PENICHE
Pool Equipment Noise Test 3/5/2026 Approved FELIPE PENICHE
Deck 3/9/2026 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/9/2026 Approved MISAEL ESPARZA
Final 3/9/2026 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Not Required MISAEL ESPARZA
Final 3/11/2026 Partial Inspection MISAEL ESPARZA
Final 4/15/2026 OK to Issue CofO MISAEL ESPARZA