4358 N CHERRY HILLS LANE 91356
Certificate Information: 4358 N CHERRY HILLS LANE 91356
- Application / Permit
- 24047-20000-01370
- Plan Check / Job No.
- B24VN18851
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- 51'0"X18'2" SWIMMING POOL WITH A 6'4"X10'6" SPA AND A FIREPIT ON PILES
- Permit Issued
- Issued on 12/30/2024
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 3/25/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2024 | MARVEL DELACRUZ |
| Corrections Issued | 10/17/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 10/24/2024 | JASON HEALEY |
| Building Plans Picked Up | 10/28/2024 | APPLICANT |
| Applicant returned to address corrections | 11/7/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 12/27/2024 | MARVEL DELACRUZ |
| Issued | 12/30/2024 | APPLICANT |
| CofO in Progress | 3/25/2026 | JOHN KIDWELL |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/27/2024 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
| Geologist | Minas,, Shant; Lic. No.: EG2607 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/14/2025 | Partial Inspection | JOHN KIDWELL |
| Pre-Inspection | 3/14/2025 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 4/17/2025 | Partial Inspection | JOHN KIDWELL |
| Deputy Other (see comments) | 4/21/2025 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 4/21/2025 | Conditional Approval | JOHN KIDWELL |
| Piling/Pier/Caisson | 4/21/2025 | Conditional Approval | JOHN KIDWELL |
| Deputy Other (see comments) | 4/28/2025 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 4/28/2025 | Partial Approval | JOHN KIDWELL |
| Piling/Pier/Caisson | 4/28/2025 | Approved | JOHN KIDWELL |
| Pre-Inspection | 8/18/2025 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 8/26/2025 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/2/2025 | Partial Approval | SEAN WIRCH |
| Deputy Other (see comments) | 9/3/2025 | Partial Approval | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 9/16/2025 | Approved | JOHN KIDWELL |
| Gas Piping or Gas Test | 9/16/2025 | Approved | JOHN KIDWELL |
| Pre-Gunite | 9/16/2025 | Approved | JOHN KIDWELL |
| Deputy Shotcrete | 9/24/2025 | Partial Approval | JOHN KIDWELL |
| Deck | 2/23/2026 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 2/23/2026 | Approved | JOHN KIDWELL |
| Equipment Noise Level | 3/12/2026 | Approved | ALFREDO FLORES |
| ELECTRICAL-Final | 3/20/2026 | Approved | JOHN KIDWELL |
| Final | 3/20/2026 | OK to Issue CofO | JOHN KIDWELL |
| PLUMBING-Final | 3/20/2026 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 4/21/2026 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 4/21/2026 | Approved | JOHN KIDWELL |