4479 E GATESIDE DR 90032
Certificate Information: 4479 E GATESIDE DR 90032
- Application / Permit
- 24047-20000-01355
- Plan Check / Job No.
- B24VN18614
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW IRREGULAR SHAPED POOL PER STANDRAD #268 PLAN AND SUPPLEMENTAL ENGINEER DETAILS 501 & 271
- Permit Issued
- Issued on 4/30/2025
- Issuing Office
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 10/3/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 4/1/2025 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/30/2025 | SERGIO MUNIZ |
| Issued | 4/30/2025 | APPLICANT |
| CofO in Progress | 4/22/2026 | LILIANA PORTILLO |
| CofO Issued | 4/23/2026 | DEROLD HAUFF |
| Permit Finaled | 4/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/3/2024 | DANIEL ABRAMYAN |
| "Q" conditions | Cleared | 4/22/2025 | GEORGIA SMITH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gunite | 5/14/2025 | Approved | LILIANA PORTILLO |
| Rough-Electrical | 5/14/2025 | Approved | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 10/20/2025 | Approved | LILIANA PORTILLO |
| Final | 10/20/2025 | Corrections Issued | LILIANA PORTILLO |
| Pre-Gunite | 10/20/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Enclosure/Fence | 11/5/2025 | Approved | LILIANA PORTILLO |
| Equipment Noise Level | 11/13/2025 | Approved | MIKE WANG |
| Final | 1/30/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Not Ready | LILIANA PORTILLO |
| Final | 4/2/2026 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Not Ready | LILIANA PORTILLO |
| Final | 4/20/2026 | OK to Issue CofO | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/20/2026 | SGSOV Approved | LILIANA PORTILLO |