6409 W COLGATE AVE 90048
Certificate Information: 6409 W COLGATE AVE 90048
- Application / Permit
- 24047-20000-01248
- Plan Check / Job No.
- B24VN16236
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL AND SPA PER LADBS STANDARD PLAN 268 AND ENGINEER DETAILS.
- Permit Issued
- Issued on 9/27/2024
- Issuing Office
- Current Status
- CofO Issued on 2/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2024 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 9/11/2024 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 9/27/2024 | ROSENDO MEDINA |
| Issued | 9/27/2024 | APPLICANT |
| CofO in Progress | 2/1/2025 | MICHAEL PELHAM |
| CofO Issued | 2/1/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/1/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/25/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 9/25/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Projekta Inc; Lic. No.: 1010761-B | 2152 DUPONT DR STE 235 IRVINE, CA 92612 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/16/2024 | Approved | MEL KHACHATOURIAN |
| Grounding or Bonding | 10/16/2024 | Approved | MEL KHACHATOURIAN |
| Pre-Gunite | 10/16/2024 | Approved | MEL KHACHATOURIAN |
| Rough-Plumbing | 10/16/2024 | Approved | MEL KHACHATOURIAN |
| Deputy Shotcrete | 10/21/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Gas Piping or Gas Test | 10/24/2024 | Approved | MEL KHACHATOURIAN |
| Enclosure/Fence | 12/19/2024 | Approved | MEL KHACHATOURIAN |
| Grounding or Bonding | 12/19/2024 | Approved | MEL KHACHATOURIAN |
| Pool Equipment Noise Test | 1/14/2025 | Approved | ANDEY CHAPARRO |
| Final | 1/17/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Final | 2/1/2025 | OK to Issue CofO | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 2/1/2025 | SGSOV Approved | MICHAEL PELHAM |