3712 N GOODLAND AVE 91604
Certificate Information: 3712 N GOODLAND AVE 91604
- Application / Permit
- 24047-20000-01193
- Plan Check / Job No.
- B24VN15038
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New irregular shaped 33' x 14' pool and Spa, per std details 268 and engineer details
- Permit Issued
- Issued on 9/17/2024
- Issuing Office
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | NAREG ATARIAN |
| Corrections Issued | 9/8/2024 | NAREG ATARIAN |
| Quality Review Completed | 9/9/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 9/10/2024 | APPLICANT |
| Applicant returned to address corrections | 9/13/2024 | NAREG ATARIAN |
| Plan Check Approved | 9/17/2024 | NAREG ATARIAN |
| Issued | 9/17/2024 | APPLICANT |
| CofO in Progress | 4/21/2026 | CHRISTOPHE COCHRAN |
| CofO Issued | 5/28/2026 | RUBEN SALAS |
| Permit Finaled | 5/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/12/2024 | BRENNEN OBETO |
| Grading Pre-Inspection | Cleared | 9/17/2024 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 3/18/2025 | Partial Inspection | MISAEL ESPARZA |
| Pre-Gunite | 3/18/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 3/25/2025 | Approved | CHRISTOPHE COCHRAN |
| Pre-Gunite | 3/25/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Pre-Gunite | 4/7/2025 | Corrections Issued | JACK KARGODORIAN |
| Pre-Gunite | 4/9/2025 | Approved | MICHEL ABAJAN |
| Deputy Shotcrete | 4/11/2025 | Conditional Approval | JUAN VALENZUELA |
| Gas Piping or Gas Test | 9/22/2025 | Approved | CHRISTOPHE COCHRAN |
| Rough-Electrical | 9/22/2025 | Approved | CHRISTOPHE COCHRAN |
| Rough-Plumbing | 9/22/2025 | Approved | CHRISTOPHE COCHRAN |
| Grounding or Bonding | 10/10/2025 | Approved | JACK KARGODORIAN |
| Enclosure/Fence | 3/5/2026 | Approved | KEVIN BERBERYAN |
| Equipment Noise Level | 3/13/2026 | Approved | ALFREDO FLORES |
| Final | 3/31/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 4/8/2026 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/8/2026 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 4/8/2026 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 4/8/2026 | SGSOV Approved | CHRISTOPHE COCHRAN |