4442 N CARPENTER AVE 91607
Certificate Information: 4442 N CARPENTER AVE 91607
- Application / Permit
- 24047-20000-01149
- Plan Check / Job No.
- B24VN14042
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN: NEW 20'x 36' POOL WITH BAJA AND 7'X7'SPA PER LA CITY STANDARD PLAN #268.
- Permit Issued
- Issued on 1/13/2025
- Issuing Office
- Current Status
- CofO Issued on 6/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2024 | KELVIN CHUONG |
| Corrections Issued | 8/28/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 9/5/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 9/11/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 9/18/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 1/1/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 1/8/2025 | MIROOSH KHACHATOORIAN |
| Issued | 1/13/2025 | APPLICANT |
| CofO in Progress | 5/15/2025 | JAVIER RAMOS JR |
| Permit Finaled | 6/18/2025 | RUBEN SALAS |
| CofO Issued | 6/18/2025 | RUBEN SALAS |
| Permit Finaled | 6/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/21/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/21/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Shotcrete | 2/26/2025 | Conditional Approval | JUAN VALENZUELA |
| Deck | 5/8/2025 | Approved | JAVIER RAMOS JR |
| Enclosure/Fence | 5/8/2025 | Approved | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Approved | JAVIER RAMOS JR |
| Final | 5/8/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Gunite | 5/8/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 5/14/2025 | OK to Issue CofO | JAVIER RAMOS JR |