24668 W OVERLAND DR 91304

Certificate Information: 24668 W OVERLAND DR 91304

Application / Permit
24047-20000-01128
Plan Check / Job No.
B24VN13425
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan New irregular shaped 28' 4" x 47' 8" pool/spa, all work done per std detail 268 and engineered details
Permit Issued
Issued on 9/30/2024
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 NAREG ATARIAN
Corrections Issued 8/25/2024 NAREG ATARIAN
Quality Review Completed 8/29/2024 OMID HEDAYAT
Applicant returned to address corrections 9/19/2024 NAREG ATARIAN
Applicant returned to address corrections 9/20/2024 NAREG ATARIAN
Plan Check Approved 9/24/2024 NAREG ATARIAN
Issued 9/30/2024 APPLICANT
CofO in Progress 10/3/2025 JEFFREY HARTLINE
No Progress 10/3/2025 HENRY KIM
CofO in Progress 10/3/2025 HENRY KIM
Permit Finaled 10/7/2025 JOHN JANSON
CofO Issued 10/7/2025 JOHN JANSON
Permit Finaled 10/7/2025 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/22/2024 RUSSELL BONVOULOIR
Miscellaneous Cleared 9/4/2024 YINGSHI HUANG

Contact Information

Contractor Wavecrest Pools Inc; Lic. No.: 881346-C53       ,
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 11/21/2024 Partial Approval JEFFREY HARTLINE
Pre-Gunite 11/21/2024 Approved JEFFREY HARTLINE
Rough-Electrical 11/21/2024 Partial Approval JEFFREY HARTLINE
Rough-Plumbing 11/21/2024 Partial Approval JEFFREY HARTLINE
Deputy Shotcrete 11/22/2024 Conditional Approval CHRIS CHRISTENSEN
Green Building Rough 11/22/2024 Approved JEFFREY HARTLINE
Pool Piping 12/19/2024 Approved JEFFREY HARTLINE
Grounding or Bonding 5/5/2025 Partial Approval JOHN COLEMAN
Rough-Electrical 5/5/2025 Partial Approval JOHN COLEMAN
Gas Piping or Gas Test 6/2/2025 Approved JEFFREY HARTLINE
Deck 6/26/2025 Approved CHRIS CHRISTENSEN
Grounding or Bonding 6/26/2025 Approved CHRIS CHRISTENSEN
Enclosure/Fence 8/13/2025 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 9/23/2025 Approved JEFFREY HARTLINE
Final 9/23/2025 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 9/23/2025 Approved JEFFREY HARTLINE
Pool Equipment Noise Test 9/23/2025 Approved ALFREDO FLORES
SGSOV-Seismic Gas S/O Valve 9/23/2025 SGSOV Approved JEFFREY HARTLINE