24668 W OVERLAND DR 91304
Certificate Information: 24668 W OVERLAND DR 91304
- Application / Permit
- 24047-20000-01128
- Plan Check / Job No.
- B24VN13425
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan New irregular shaped 28' 4" x 47' 8" pool/spa, all work done per std detail 268 and engineered details
- Permit Issued
- Issued on 9/30/2024
- Issuing Office
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | NAREG ATARIAN |
| Corrections Issued | 8/25/2024 | NAREG ATARIAN |
| Quality Review Completed | 8/29/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/19/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 9/20/2024 | NAREG ATARIAN |
| Plan Check Approved | 9/24/2024 | NAREG ATARIAN |
| Issued | 9/30/2024 | APPLICANT |
| CofO in Progress | 10/3/2025 | JEFFREY HARTLINE |
| No Progress | 10/3/2025 | HENRY KIM |
| CofO in Progress | 10/3/2025 | HENRY KIM |
| Permit Finaled | 10/7/2025 | JOHN JANSON |
| CofO Issued | 10/7/2025 | JOHN JANSON |
| Permit Finaled | 10/7/2025 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/22/2024 | RUSSELL BONVOULOIR |
| Miscellaneous | Cleared | 9/4/2024 | YINGSHI HUANG |
Contact Information
| Contractor | Wavecrest Pools Inc; Lic. No.: 881346-C53 | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 11/21/2024 | Partial Approval | JEFFREY HARTLINE |
| Pre-Gunite | 11/21/2024 | Approved | JEFFREY HARTLINE |
| Rough-Electrical | 11/21/2024 | Partial Approval | JEFFREY HARTLINE |
| Rough-Plumbing | 11/21/2024 | Partial Approval | JEFFREY HARTLINE |
| Deputy Shotcrete | 11/22/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 11/22/2024 | Approved | JEFFREY HARTLINE |
| Pool Piping | 12/19/2024 | Approved | JEFFREY HARTLINE |
| Grounding or Bonding | 5/5/2025 | Partial Approval | JOHN COLEMAN |
| Rough-Electrical | 5/5/2025 | Partial Approval | JOHN COLEMAN |
| Gas Piping or Gas Test | 6/2/2025 | Approved | JEFFREY HARTLINE |
| Deck | 6/26/2025 | Approved | CHRIS CHRISTENSEN |
| Grounding or Bonding | 6/26/2025 | Approved | CHRIS CHRISTENSEN |
| Enclosure/Fence | 8/13/2025 | Approved | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 9/23/2025 | Approved | JEFFREY HARTLINE |
| Final | 9/23/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Green Building Final | 9/23/2025 | Approved | JEFFREY HARTLINE |
| Pool Equipment Noise Test | 9/23/2025 | Approved | ALFREDO FLORES |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Approved | JEFFREY HARTLINE |