3721 S DEGNAN BLVD 90018
Certificate Information: 3721 S DEGNAN BLVD 90018
- Application / Permit
- 24047-20000-01114
- Plan Check / Job No.
- B24VN12978
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12' X 22' SWIMMING POOL PER LA CITY STANDARD PLAN #268.
- Permit Issued
- Issued on 12/17/2024
- Issuing Office
- Current Status
- CofO Issued on 4/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 8/13/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 12/17/2024 | GIOVANNY CHAVEZ |
| Issued | 12/17/2024 | APPLICANT |
| CofO in Progress | 4/21/2026 | LUIS CASTRO |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
| CofO Issued | 4/26/2026 | DEROLD HAUFF |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/12/2024 | TINA MIRANDA |
Contact Information
| Contractor | Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 | 978 NORTH AMEILA AVE SAN DIMAS, CA 91773 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/11/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Rough | 4/11/2025 | Approved | LUIS CASTRO |
| Pre-Gunite | 4/11/2025 | Corrections Issued | LUIS CASTRO |
| Rough-Electrical | 4/11/2025 | Partial Approval | LUIS CASTRO |
| Rough-Plumbing | 4/11/2025 | Partial Approval | LUIS CASTRO |
| Pre-Gunite | 4/21/2025 | Approved | LUIS CASTRO |
| Deck | 6/30/2025 | Approved | LUIS CASTRO |
| Enclosure/Fence | 7/14/2025 | Approved | WAYNE REGESTER |
| Pool Equipment Noise Test | 7/30/2025 | Approved | EUSEBIO GUZMAN |
| Excavation/Setback/Form/Re-Bar | 8/4/2025 | Approved | LUIS CASTRO |
| Final | 8/4/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 8/4/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Approved | LUIS CASTRO |
| Final | 8/15/2025 | Corrections Issued | LUIS CASTRO |
| Final | 9/5/2025 | Corrections Issued | LUIS CASTRO |
| Final | 4/20/2026 | OK to Issue CofO | LUIS CASTRO |