400 N BONHILL ROAD 90049

Certificate Information: 400 N BONHILL ROAD 90049

Application / Permit
24047-20000-01103
Plan Check / Job No.
B24VN12244
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 12'6" X 12'6" SPA , ALL WORK PER ENGINEERING- SEE COMMENTS
Permit Issued
Issued on 10/28/2024
Issuing Office
Current Status
CofO Issued on 4/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 RARES BODEA
Corrections Issued 8/13/2024 RARES BODEA
Quality Review Completed 8/15/2024 STEVEN KIM
Building Plans Picked Up 8/19/2024 APPLICANT
Applicant returned to address corrections 9/26/2024 RARES BODEA
Applicant returned to address corrections 10/10/2024 RARES BODEA
Applicant returned to address corrections 10/22/2024 RARES BODEA
Plan Check Approved 10/28/2024 RARES BODEA
Issued 10/28/2024 APPLICANT
CofO in Progress 3/27/2026 KEVIN SARGSYAN
Permit Finaled 4/3/2026 RICHARD STEINBACH
CofO Issued 4/3/2026 RICHARD STEINBACH
Permit Finaled 4/3/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/26/2024 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/14/2024 Partial Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/25/2025 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/26/2025 Corrections Issued JESUS RODRIGUEZ
Deputy Other (see comments) 3/14/2025 Conditional Approval JESUS RODRIGUEZ
Deputy Other (see comments) 3/17/2025 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 3/17/2025 Partial Approval KEVIN SARGSYAN
Pre-Gunite 3/17/2025 Conditional Approval KEVIN SARGSYAN
Rough-Electrical 3/17/2025 Partial Approval KEVIN SARGSYAN
Rough-Plumbing 3/17/2025 Partial Approval KEVIN SARGSYAN
Deputy Other (see comments) 3/25/2025 Conditional Approval KEVIN SARGSYAN
Rough-Electrical 8/20/2025 Not Ready for Inspection KEVIN SARGSYAN
Rough-Plumbing 8/20/2025 Not Ready for Inspection KEVIN SARGSYAN
Grounding or Bonding 10/24/2025 Approved KEVIN SARGSYAN
Enclosure/Fence 2/5/2026 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 3/18/2026 Approved KEVIN SARGSYAN
Pool Equipment Noise Test 3/18/2026 Approved EUSEBIO GUZMAN
SGSOV-Seismic Gas S/O Valve 3/18/2026 SGSOV Approved KEVIN SARGSYAN
Final 3/27/2026 OK to Issue CofO KEVIN SARGSYAN
Pre-Gunite 3/27/2026 Approved KEVIN SARGSYAN