400 N BONHILL ROAD 90049
Certificate Information: 400 N BONHILL ROAD 90049
- Application / Permit
- 24047-20000-01103
- Plan Check / Job No.
- B24VN12244
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12'6" X 12'6" SPA , ALL WORK PER ENGINEERING- SEE COMMENTS
- Permit Issued
- Issued on 10/28/2024
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | RARES BODEA |
| Corrections Issued | 8/13/2024 | RARES BODEA |
| Quality Review Completed | 8/15/2024 | STEVEN KIM |
| Building Plans Picked Up | 8/19/2024 | APPLICANT |
| Applicant returned to address corrections | 9/26/2024 | RARES BODEA |
| Applicant returned to address corrections | 10/10/2024 | RARES BODEA |
| Applicant returned to address corrections | 10/22/2024 | RARES BODEA |
| Plan Check Approved | 10/28/2024 | RARES BODEA |
| Issued | 10/28/2024 | APPLICANT |
| CofO in Progress | 3/27/2026 | KEVIN SARGSYAN |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
| CofO Issued | 4/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/26/2024 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/14/2024 | Partial Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/25/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/26/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Other (see comments) | 3/14/2025 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Other (see comments) | 3/17/2025 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/17/2025 | Partial Approval | KEVIN SARGSYAN |
| Pre-Gunite | 3/17/2025 | Conditional Approval | KEVIN SARGSYAN |
| Rough-Electrical | 3/17/2025 | Partial Approval | KEVIN SARGSYAN |
| Rough-Plumbing | 3/17/2025 | Partial Approval | KEVIN SARGSYAN |
| Deputy Other (see comments) | 3/25/2025 | Conditional Approval | KEVIN SARGSYAN |
| Rough-Electrical | 8/20/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Rough-Plumbing | 8/20/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Grounding or Bonding | 10/24/2025 | Approved | KEVIN SARGSYAN |
| Enclosure/Fence | 2/5/2026 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/18/2026 | Approved | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 3/18/2026 | Approved | EUSEBIO GUZMAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 3/27/2026 | OK to Issue CofO | KEVIN SARGSYAN |
| Pre-Gunite | 3/27/2026 | Approved | KEVIN SARGSYAN |