4852 N TILDEN AVE 91423
Certificate Information: 4852 N TILDEN AVE 91423
- Application / Permit
- 24047-20000-01092
- Plan Check / Job No.
- B24VN12464
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12' X 25' POOL PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 10/30/2024
- Issuing Office
- Current Status
- CofO Issued on 5/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 8/8/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 10/30/2024 | YAQUB MIRZA |
| Issued | 10/30/2024 | APPLICANT |
| CofO in Progress | 4/17/2025 | MISAEL ESPARZA |
| Permit Finaled | 5/13/2025 | RUBEN SALAS |
| CofO Issued | 5/13/2025 | RUBEN SALAS |
| Permit Finaled | 5/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/24/2024 | TINA MIRANDA |
| Construction within easement | Cleared | 10/24/2024 | TINA MIRANDA |
Contact Information
| Contractor | Smart Swim Pool Construction Inc; Lic. No.: 1089412-C53 | 19634 VENTURA BLVD STE 212 TARZANA, CA 91356 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/13/2024 | Approved | MISAEL ESPARZA |
| Deputy Shotcrete | 12/16/2024 | Conditional Approval | JUAN VALENZUELA |
| Gas Piping or Gas Test | 12/23/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Electrical | 12/23/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Piping or Gas Test | 12/30/2024 | Approved | MISAEL ESPARZA |
| Rough-Electrical | 12/30/2024 | Approved | MISAEL ESPARZA |
| Rough-Plumbing | 12/30/2024 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 1/23/2025 | Corrections Issued | JACK KARGODORIAN |
| Enclosure/Fence | 2/20/2025 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 4/7/2025 | Approved | MISAEL ESPARZA |
| Final | 4/7/2025 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Approved | MISAEL ESPARZA |
| Equipment Noise Level | 4/11/2025 | Approved | ALFREDO FLORES |
| Final | 4/16/2025 | OK to Issue CofO | MISAEL ESPARZA |