336 N ARDEN BLVD 90004

Certificate Information: 336 N ARDEN BLVD 90004

Application / Permit
24047-20000-01048
Plan Check / Job No.
B24VN11141
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 11' X 13'-3" POOL WITH A 11' X 6'-9" SPA PER CITY OF LA STANDARD PLAN #268.
Permit Issued
Issued on 11/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 7/29/2024 MIROOSH KHACHATOORIAN
Corrections Issued 7/29/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 11/19/2024 ALEC MOUSAKHANIAN
Issued 11/19/2024 APPLICANT
CofO in Progress 9/4/2025 JEFFREY MEAD
Permit Finaled 9/7/2025 DEROLD HAUFF
CofO Issued 9/7/2025 DEROLD HAUFF
Permit Finaled 9/7/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 11/14/2024 RIDWAN HARDY
Construction within easement Cleared 11/14/2024 RIDWAN HARDY

Contact Information

Contractor Coastal Aquatic Creations; Lic. No.: 697943-C53 11730 GATEWAY BLVD      LOS ANGELES, CA 90064
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/13/2025 Approved JOSH MEISTER
Gas Piping or Gas Test 6/13/2025 Approved JOSH MEISTER
Pre-Gunite 6/13/2025 Approved JOSH MEISTER
Rough-Electrical 6/13/2025 Approved JOSH MEISTER
Rough-Plumbing 6/13/2025 Approved JOSH MEISTER
Deputy Shotcrete 6/17/2025 Conditional Approval JEFFREY MEAD
Deck 7/16/2025 Partial Approval BRENDAN MORELLI
Enclosure/Fence 7/29/2025 Conditional Approval JEFFREY MEAD
Pool Equipment Noise Test 8/26/2025 Approved MIKE WANG
Final 8/27/2025 Corrections Issued JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/27/2025 SGSOV Not Ready JEFFREY MEAD
Final 8/29/2025 Not Ready for Inspection RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Not Ready RONNIE MINDANAO
Final 9/3/2025 OK to Issue CofO JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Approved JEFFREY MEAD