1568 N MURRAY CIR 90026

Certificate Information: 1568 N MURRAY CIR 90026

Application / Permit
24047-20000-00950
Plan Check / Job No.
B24VN09782
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(4) Pool/Spa - Public
Work Description
NEW 12'-11" x 24'-0" POOL PER LA STANDARD PLAN #268 AND SUPPLEMENTAL DETAILS.
Permit Issued
Issued on 8/2/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 JESSE ARELLANO
Corrections Issued 7/18/2024 JESSE ARELLANO
Building Plans Picked Up 7/25/2024 APPLICANT
Plan Check Approved 8/2/2024 SARKIS HARABEDIAN
Issued 8/2/2024 APPLICANT
CofO in Progress 4/4/2025 HAMIK HARTOUNIAN
Permit Finaled 4/5/2025 DEROLD HAUFF
CofO Issued 4/5/2025 DEROLD HAUFF
Permit Finaled 4/5/2025 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 7/31/2024 DORIAN AGUILAR

Contact Information

Contractor Coastal Aquatic Creations; Lic. No.: 697943-C53 11730 GATEWAY BLVD      LOS ANGELES, CA 90064
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/22/2024 Approved FREDDIE RIVERA
Gas Piping or Gas Test 8/22/2024 Approved FREDDIE RIVERA
Pool Piping 8/22/2024 Approved FREDDIE RIVERA
Pre-Gunite 8/22/2024 Approved FREDDIE RIVERA
Rough-Electrical 8/22/2024 Partial Approval FREDDIE RIVERA
Rough-Plumbing 8/22/2024 Approved FREDDIE RIVERA
Deputy Shotcrete 8/23/2024 Approved HAMIK HARTOUNIAN
Deck 10/3/2024 Approved HAMIK HARTOUNIAN
Enclosure/Fence 10/18/2024 Approved LUIS CASTRO
Pool Equipment Noise Test 10/24/2024 Approved ANDEY CHAPARRO
Final 12/18/2024 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/18/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Final 2/14/2025 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Approved HAMIK HARTOUNIAN
Final 3/25/2025 Corrections Issued HAMIK HARTOUNIAN
Final 4/2/2025 Corrections Issued HAMIK HARTOUNIAN
Final 4/4/2025 OK to Issue CofO HAMIK HARTOUNIAN