5714 N BUFFALO AVE 91401

Certificate Information: 5714 N BUFFALO AVE 91401

Application / Permit
24047-20000-00911
Plan Check / Job No.
B24VN09368
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New 15'W x 29'L x 4'6"D swimming pool with a pool cover and 7'W x 7'L x 3'-6"D SPA per LA City standard plan #270
Permit Issued
Issued on 1/27/2025
Issuing Office
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 CARLOS MONTES
Corrections Issued 7/4/2024 CARLOS MONTES
Applicant returned to address corrections 7/25/2024 HANS SANTIAGO
Applicant returned to address corrections 12/16/2024 CARLOS MONTES
Plan Check Approved 1/26/2025 ADAM HEGAZI
Issued 1/27/2025 APPLICANT
CofO in Progress 8/22/2025 RYAN SALAZAR
Permit Finaled 8/27/2025 RUBEN SALAS
CofO Issued 8/27/2025 RUBEN SALAS
Permit Finaled 8/27/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 10/2/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu Dan; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 2/24/2025 Approved ROBERTO PALACIOS-LOPEZ
Deputy Shotcrete 2/25/2025 Conditional Approval RAUL OLAGI
Gas Piping or Gas Test 3/25/2025 Approved RYAN SALAZAR
Pool Piping 3/25/2025 Approved RYAN SALAZAR
Rough-Electrical 3/25/2025 Approved RYAN SALAZAR
Grounding or Bonding 6/2/2025 Approved RYAN SALAZAR
Enclosure/Fence 6/30/2025 Approved RYAN SALAZAR
Equipment Noise Level 8/14/2025 Approved FELIPE PENICHE
Pool Equipment Noise Test 8/14/2025 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 8/18/2025 Approved RYAN SALAZAR
Final 8/18/2025 OK to Issue CofO RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/18/2025 SGSOV Approved RYAN SALAZAR